Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jun 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
19 Jun 2025 | FHTC providing started - 2281 Nos; Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr work held up due to heavy rain | Mattannur WS Sn | |
18 Jun 2025 | FHTC providing started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
14 May 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
30 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
16 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
01 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
16 Mar 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
07 Mar 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn | |
25 Feb 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn |