| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Sep 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 19 Aug 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 31 Jul 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 21 Jul 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 30 Jun 2025 | FHTCs provided - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 19 Jun 2025 | FHTC providing started - 2281 Nos; Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr work held up due to heavy rain | Mattannur WS Sn | |
| 18 Jun 2025 | FHTC providing started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 14 May 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 30 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 16 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn |