| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Jun 2025 | FHTC providing started - 2281 Nos Pipe line laid - 21159mtr, road restoration work done upto - 5000mtr: work held up due to heavy rain | Mattannur WS Sn | |
| 14 May 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 30 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 16 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 01 Apr 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 16 Mar 2025 | FHTC providing started - 1021 Nos Pipe line laid - 12300mtr | Mattannur WS Sn | |
| 07 Mar 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn | |
| 25 Feb 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn | |
| 11 Feb 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn | |
| 28 Jan 2025 | FHTC providing started - 824 Nos Pipe line laid - 8400mtr | Mattannur WS Sn |