Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Feb 2021 Package updated Palakkad Proj Dn AE 4
29 Jan 2021 1. RWPM 400mm DI-K9-5839.50m supplied 5393m laid. 2. Filter House -A) Filter bed Structural work completed. Plastering and tile work completed. Laterals fixed. Filter media filling completed. B) Wash water tank - work completed C) Painting ,Plastering, Tile works completed 3.Aerator - Plastering completed. First coat painting finished 4.Flash mixer - Structural work completed,Plastering completed. Painting going on 5.CW Sump - Plastering completed. 6. Chlorine and CW Pump house: structural and plastering works completed. First coat painting completed. Hoist for Chlorine tonner fixed 7. Chemical House: Structural completed . Plastering and brick work completed. Floor tiling works completed 8. Clariflocculator: Structure completed. Electro mechanical work started. 9. 350 mm DI K9 CWPM to Mannur OHSR 4831.50m laid out of 4965m . 10. 200mm DI K9 CWPM -6259m supplied 6012.05m laid out of 6100m . 11.11 LL OHSR - Painting first coat completed, Pump house work completed. 12.8 LL OHSR- Structural work completed, Plastering work in progress 13. HDD work in Njavalinkadavu for railway line crossing : Casing and RW pumping main pipe laid. 14. CF pump erection works completed at Mannur OHSR. 15. VT pump erection at Well cum pump house in progress 16. CF pump erection works completed at Mannur WTP 17. Transformer base concrete works started Palakkad Proj Dn AE 4
26 Jan 2021 1. RWPM 400mm DI-K9-5839.50m supplied 5393m laid. 2. Filter House -A) Filter bed Structural work completed. Plastering and tile work completed. Laterals fixed. Filter media filling completed. B) Wash water tank - work completed C) Painting ,Plastering, Tile works completed 3.Aerator - Plastering completed. First coat painting finished 4.Flash mixer - Structural work completed,Plastering completed. Painting going on 5.CW Sump - Plastering completed. 6. Chlorine and CW Pump house: structural and plastering works completed. First coat painting completed. Hoist for Chlorine tonner fixed 7. Chemical House: Structural completed . Plastering and brick work completed. Floor tiling works completed 8. Clariflocculator: Structure completed. Electro mechanical work started. 9. 350 mm DI K9 CWPM to Mannur OHSR 4831.50m laid out of 4965m . 10. 200mm DI K9 CWPM -6259m supplied 6012.05m laid out of 6100m . 11.11 LL OHSR - Painting first coat completed, Pump house work completed. 12.8 LL OHSR- Structural work completed, Plastering work in progress 13. HDD work in Njavalinkadavu for railway line crossing : Casing and RW pumping main pipe laid. 14. CF pump erection works completed at Mannur OHSR. 15. VT pump erection at Well cum pump house in progress 16. CF pump erection works completed at Mannur WTP Palakkad Proj Dn AE 4
15 Dec 2020 1. RWPM 400mm DI-K9-5839.50m supplied 5393m laid. 2. Filter House -A) Filter bed Structural work completed. Plastering and tile work completed. Laterals fixed. Filter media filling in progress B) wash water tank - work completed C) Painting ,Plastering, Tile works on completion stage 3.Aerator - Plastering completed. First coat painting finished 4.Flash mixer - Structural work completed,Plastering completed. Painting going on 5.CW Sump - Plastering completed. 6. Chlorine and CW Pump house: structural and plastering works completed. First coat painting completed. Hoist for Chlorine tonner fixed 7. Chemical House: Structural completed . Plastering and brick work completed. Floor tiling works finishing stage 8. Clariflocculator: Structure completed. Electro mechanical work started. 9. 350 mm DI K9 CWPM to Mannur OHSR 4831.50m laid out of 4965m . 10. 200mm DI K9 CWPM -6259m supplied 5337.8m laid out of 6100m . 11.11 LL OHSR - Painting first coat completed, Pump house work completed. 12.8 LL OHSR- Structural work completed, Plastering work in progress 13. HDD work in Njavalinkadavu for railway line crossing : Casing and RW pumping main pipe laid. 14. CF pump erection works started at Mannur OHSR. RCC for foundation completed. VT pump erection at Well cum pump house in progress Palakkad Proj Dn AE 4
04 Dec 2020 1. RWPM 400mm DI-K9-5839.50m supplied 5393m laid. 2. Filter House -A) Filter bed Structural work completed. Plastering and tile work completed. Laterals fixed B) wash water tank - work completed C) Painting ,Plastering, Tile works on completion stage 3.Aerator - Plastering completed. First coat painting finished 4.Flash mixer - Structural work completed,Plastering completed. Painting going on 5.CW Sump - Plastering completed. 6. Chlorine and CW Pump house: structural and plastering works completed. First coat painting completed. Hoist for Chlorine tonner fixed 7. Chemical House: Structural completed . Plastering and brick work completed. Floor tiling works finishing stage 8. Clariflocculator: Structure completed. Electro mechanical work finished. 9. 350 mm DI K9 CWPM to Mannur OHSR 4831.50m laid out of 4965m . 10. 200mm DI K9 CWPM -6259m supplied 4417m laid out of 6100m . 11.11 LL OHSR - Painting first coat completed, Pump house work completed. 12.8 LL OHSR- Structural work completed, Plastering work in progress 13. HDD work in Njavalinkadavu for railway line crossing : Casing and RW pumping main pipe laid. 14. CF pump erection works started at Mannur OHSR. RCC for foundation completed. VT pump erection at Well cum pump house in progress Palakkad Proj Dn AE 4
13 Nov 2020 1. RWPM 400mm DI-K9-5839.50m supplied 5393m laid. 2. Filter House -A) Filter bed Structural work completed. Plastering and tile work completed. Piping works also in progress B) wash water tank - work completed C) Painting ,Plastering, Tile works on completion stage 3.Aerator - Plastering completed 4.Flash mixer - Structural work completed,Plastering completed. 5.CW Sump - Plastering completed. 6. Chlorine and CW Pump house: structural and plastering works completed. First coat painting completed. Hoist for Chlorine tonner fixed 7. Chemical House: Structural completed . Plastering and brick work completed. Floor tiling works finishing stage 8. Clariflocculator: Structural and plastering completed 9. 350 mm DI K9 CWPM to Mannur OHSR 4831.50m laid. 10. 200mm DI K9 CWPM -6259m supplied 3086.3m laid. 11.11 LL OHSR - Painting first coat completed, Pump house work completed. 12.8 LL OHSR- Structural work completed 13. HDD work in Njavalinkadavu for railway line crossing : Casing and RW pumping main pipe laid. 14. CF pump erection works started at Mannur OHSR Palakkad Proj Dn AE 4