| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Mar 2021 | 1.Sludge pipe laying completed 2. Compound wall plastering 11LL OHSR finished. Painting of compound wall progressing 3. Keralassery 8LL OHSR Plastering completed. Painting started 4. Electro mechanical works completed at WTP 5. transformer erection progressing 6. Power allocation charges paid to KSEB for WTP and Mannur WTP | Palakkad Proj Dn AE 4 | |
| 25 Feb 2021 | Transformer work progressing | Palakkad Proj Dn AE 4 | |
| 24 Feb 2021 | Transformer erection work resumed | Palakkad Proj Dn AE 4 | |
| 23 Feb 2021 | 1.Sludge pipe laying progressing 300m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 20 Feb 2021 | 1.Sludge pipe laying progressing 290m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 19 Feb 2021 | 1.Sludge pipe laying progressing 280m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 18 Feb 2021 | 1.Sludge pipe laying progressing 260m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 15 Feb 2021 | 1. Sludge pipe laying progressing 220m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 14 Feb 2021 | 1. Sludge pipe laying progressing 200m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 | |
| 13 Feb 2021 | 1. Sludge pipe laying progressing 200m laid 2. Compound wall plastering 11LL OHSR finished. Painting started 3. Keralassery 8LL OHSR Plastering progressing 4. Electro mechanical works progressing at WTP | Palakkad Proj Dn AE 4 |