- Home
- NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALA...
NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALASSERY AND MANKARA PANCHAYTHS IN PALAKKAD DISTRICT
| Project |
NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALASSERY AND MANKARA PANCHAYTHS IN PALAKKAD DISTRICT |
| Project Code |
PKDNABARD1217641 |
| Type |
Main project |
| Funding Agency |
NABARD |
| Category |
NABARD |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-98 (01) |
| Description |
Comprehensive water supply scheme to Mannur, Keralassery and Mankara Panchayaths in Palakkad district |
| Status |
Completed |
| District |
Palakkad |
| Executing Office |
Palakkad Project Dn |
| AS Amount (Rs) |
253000000
|
| AS Number |
1070/2017/WRD |
| TS Amount (Rs) |
253000000 |
| TS Number |
TS/2018-2019/2018/158 |
| Total Bill Submitted (Rs) |
205933021 |
| Total Bill Paid (Rs) |
205933021 |
| Population Benefitted |
70636 |
| Capacity in MLD |
10.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Mannur, Keralassery, Mankara Panchayath
|
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
CWSS to Mannur,Keralassery and Mankara panchayaths of Palakkad District -Phase-I |
Project Division Palakkad |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Feb 2022 |
Completed |
Palakkad Proj Dn AE 4 |
|
| 07 Nov 2021 |
trial run progressing |
Palakkad Project Dn EE |
|
| 05 Nov 2021 |
Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel |
Palakkad Proj Dn AE 4 |
|
| 29 Oct 2021 |
Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel |
Palakkad Proj Dn AE 4 |
|
| 23 Oct 2021 |
Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel |
Palakkad Proj Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
07/01/2019 |
| Scheduled date of Completion of the Project |
31 Mar 2021 |
| Expected date of Completion |
29/10/2021 |
Processing Dates
| AS Date |
30 Dec 2017 |
| TS Date |
10 Apr 2018 |