Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALASSERY AND MANKARA PANCHAYTHS IN PALAKKAD DISTRICT

Project NABARD-RIDF-XXIII-CWSS TO MANNUR, KERALASSERY AND MANKARA PANCHAYTHS IN PALAKKAD DISTRICT
Project Code PKDNABARD1217641
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme 4215-01-102-98 (01)
Description Comprehensive water supply scheme to Mannur, Keralassery and Mankara Panchayaths in Palakkad district
Status Completed
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 253000000
AS Number 1070/2017/WRD
TS Amount (Rs) 253000000
TS Number TS/2018-2019/2018/158
Total Bill Submitted (Rs) 205933021
Total Bill Paid (Rs) 205933021
Population Benefitted 70636
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Mannur, Keralassery, Mankara Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 CWSS to Mannur,Keralassery and Mankara panchayaths of Palakkad District -Phase-I Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2022 Completed Palakkad Proj Dn AE 4
07 Nov 2021 trial run progressing Palakkad Project Dn EE
05 Nov 2021 Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel Palakkad Proj Dn AE 4
29 Oct 2021 Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel Palakkad Proj Dn AE 4
23 Oct 2021 Trial run 1)Njavolinkadavu- Intake well area-Raw water pump erection completed, Piping works completed , 200kVA Transformer supplied and erected. KSEB Power allocation completed. Motors energised. RWPM charged2) Road crossing at Pathiripala along irrigation Canal finished 3) WTP works completed, Power allocation works by KSEB completed 4) Clear water pumping line laying works completed. Line charging works going on 5) 11 LL OHSR and pump house at Mannur works completed. Pumps erection completed energisation work started by KSEB 6) Clear Water pumping line laying works completed 7) 8LL OHSR at Keralassery compound wall work and Painting work completed 8) Flow meters fixed at WTP and Intakewel Palakkad Proj Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/01/2019
Scheduled date of Completion of the Project 31 Mar 2021
Expected date of Completion 29/10/2021

Processing Dates

AS Date 30 Dec 2017
TS Date 10 Apr 2018

Other details

Project Officers View