| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 17 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 15 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 10 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 07 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattapana AE 1 | |
| 03 Feb 2023 | 1866m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 31 Jan 2023 | 1512m of 100mm GI Pipes laid and to do the Welding work at site. | Kattapana AE 1 | |
| 28 Jan 2023 | 1428m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 25 Jan 2023 | 786m of 100mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 21 Jan 2023 | 384m of 100mm GI Pipes laid. | Kattappana AEE 1 |