| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Feb 2021 | Process of obtaining power allocation from KSEB being done in both RW Pump house and WTP. All testing fees to KSEB have remitted and awaiting power connection. | Malappuram Project Dn AE2 | |
| 02 Feb 2021 | The initial inspection fee of transformers and electrical installations remitted to KSEB. | Malappuram Project Dn AE2 | |
| 25 Jan 2021 | The work is in Final stages and pumping can be started after obtaining the power allocation from KSEB | Malappuram Project Dn AE2 | |
| 31 Dec 2020 | The Erection of Electrical equipment completed. Power connection to be obtained | Malappuram Project Dn AE2 | |
| 16 Aug 2020 | Work in progress. | Malappuram Project Dn AE2 | |
| 11 Aug 2020 | Work in progress | Malappuram Project Dn AE2 | |
| 03 Aug 2020 | The Electrical work is in progress. | Malappuram Project Dn AE2 | |
| 01 Jul 2020 | All Electro mechanical items supplied, but erection to be completed. Sub station building 95 % completed. The power allocation works is in progress. | Malappuram Project Dn AE2 |