| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2021 | Charging on motors at WTP in progressing | Malappuram Project Dn AE2 | |
| 14 Jun 2021 | Charging various components in wtp is progressing. Heavy rain hinder the work. | Malappuram Project Dn AE2 | |
| 11 Jun 2021 | Power connection obtained at WTP site Thiruvali today. Charging of WTP and sump is in progress. | Malappuram Project Dn AE2 | |
| 10 Jun 2021 | Power obtained at intake well, Aryanthodika and test pumping to WTP successfully completed. The power connection at WTP Thiruvali will obtained tomorrow ( 11.06.2021) | Malappuram Project Dn AE2 | |
| 31 May 2021 | Power obtained at intake well, Aryanthodika and test pumping to WTP successfully completed. The CD amount remitted for power connection on 29.05.2021 and can test the pumps at WTP Thiruvali soon. | Malappuram Project Dn AE2 | |
| 31 Mar 2021 | Power obtained at intake well, Aryanthodika and test pumping to WTP successfully completed. The approval of EI obtained for WTP site Thiruvali, and CD to be remitted for Energisation. | Malappuram Project Dn AE2 | |
| 19 Mar 2021 | Power obtained at intake well, Aryanthodika. Arrangement for test pumping is carrying on | Malappuram Project Dn AE2 | |
| 07 Mar 2021 | Power at RW pump house will arrived soon. Agreement with KSEB for obtaining connection is scheduled to execute on tomorrow | Malappuram Project Dn AE2 | |
| 04 Mar 2021 | stringent followup done for energization at RWPM pump house and booster station at WTP | Malappuram Project Dn AE2 | |
| 01 Mar 2021 | Inspection of Electrical Inspectorate completed at RW Pump house and requested to KSEB for intimating the amount to be remitted as CD. Requested to EI for immediate energisaion at Both pumping stations. | Malappuram Project Dn AE2 |