State plan - CRWSS to Thiruvali and Adjoining Villages- Phase 1, Thiruvali Village - Providing Raw water Pump set, Clear water Pump set, Transformers, Gantry Girder and Power Line Extension .

Project State plan - CRWSS to Thiruvali and Adjoining Villages- Phase 1, Thiruvali Village - Providing Raw water Pump set, Clear water Pump set, Transformers, Gantry Girder and Power Line Extension .
Project Code MLPGOK1217551
Type Main project
Category State plan
Description Phase I - Thiruvali village . Providing raw water pump setsd, Clear water pump sets, Transformers, gantry girders and power line extension
District Malappuram
Execution Malappuram Project Dn
AS Amount (Rs) 20000000.00
Total Bill Submitted (Rs) 7660791.00
Total Bill Paid (Rs) 0.00
Coverage All wards of Thiruvali Panchayath and a part of Wandoor Panchayath

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Mar 2021 Power obtained at intake well, Aryanthodika and test pumping to WTP successfully completed. The approval of EI obtained for WTP site Thiruvali, and CD to be remitted for Energisation. Malappuram Project Dn AE2
19 Mar 2021 Power obtained at intake well, Aryanthodika. Arrangement for test pumping is carrying on Malappuram Project Dn AE2
07 Mar 2021 Power at RW pump house will arrived soon. Agreement with KSEB for obtaining connection is scheduled to execute on tomorrow Malappuram Project Dn AE2
04 Mar 2021 stringent followup done for energization at RWPM pump house and booster station at WTP Malappuram Project Dn AE2
01 Mar 2021 Inspection of Electrical Inspectorate completed at RW Pump house and requested to KSEB for intimating the amount to be remitted as CD. Requested to EI for immediate energisaion at Both pumping stations. Malappuram Project Dn AE2

No project review have been added to this project

Packages

No. Project Name Location View
1 Providing Raw water Pump set, Clear water Pump set, Transformers, Gantry Girder and Power Line Extension . Project Division Malappuram

Duration & Sanction dates

Date of Sanction 20/12/2017
Date of start 01/12/2018
Expected date of Completion 30/09/2020

Other details

Project Officers View
Funding Agency GOK

Processing Dates

AS Date 20 Dec 2017
TS Date 07 Jul 2018

Approval Dates

Workorder Date 01 Dec 2018
Agreement Date 24 Dec 2018

Location