19 Jun 2023 Agreement Executed. Pipe supplied ,PWD and Corporation road cutting permission to be obtained Perlassery Sn 2 AE
16 Jun 2023 Agreement Executed. Pipe supplied ,PWD and Corporation road cutting permission to be obtained Perlassery Sn 2 AE
13 Jun 2023 Agreement Executed. Pipe supplied ,PWD and Corporation road cutting permission to be obtained. Perlassery Sn 2 AE
08 Jun 2023 Agreement Executed. Pipe supplied ,PWD and Corporation road cutting permission to be obtained. Perlassery Sn 2 AE
01 Jun 2023 Agreement Executed. Pipe supplied ,PWD and Corporation road cutting permission to be obtained. Perlassery Sn 2 AE
24 May 2023 agreement executed. Pipe supplied ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
18 May 2023 agreement executed. Pipe supplied ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
15 May 2023 agreement executed. Pipe supplied ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
10 May 2023 agreement executed. Pipe supplied ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
02 May 2023 agreement executed. Pipe supplied ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE