Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jan 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
30 Dec 2022 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
26 Dec 2022 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
21 Dec 2022 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
15 Dec 2022 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
11 Dec 2022 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
06 Dec 2022 Agreement executed Perlassery Sn 2 AE
26 Nov 2022 Agreement executed Perlassery Sn 2 AE
01 Nov 2022 Work order issued on 31.10.2022 Kannur PH Dn EE
26 Oct 2022 Work tendered again after estimate revision. Tender to be opened on 27.10.2022 Kannur PH Dn EE