Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Mar 2023 Agreement executed.Pipe test at factory arranged ,PWD and CORPORATION ROAD CUTTING PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
04 Mar 2023 Agreement executed.Pipe test at factory arranged ,PWD and CORPORATION PERMISSION TO BE OBTAINED Perlassery Sn 2 AE
27 Feb 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
21 Feb 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
17 Feb 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
10 Feb 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
02 Feb 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
29 Jan 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
19 Jan 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE
07 Jan 2023 Agreement executed.Pipe test at factory arranged Perlassery Sn 2 AE