Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Oct 2023 | Proposal submitted for revised AS. | Perlassery Sn 2 AE | |
04 Oct 2023 | Proposal submitted for revised AS. | Kannur PH Dn EE | |
03 Oct 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
27 Sep 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
20 Sep 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
13 Sep 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
01 Sep 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
24 Aug 2023 | PWD/Corporation road cutting permission to be obtained. | Perlassery Sn 2 AE | |
17 Aug 2023 | PWD/Corporation road cutting permission to be obtained. | Kannur PH Dn EE | |
09 Aug 2023 | PWD/Corporation road cutting permission to be obtained | Perlassery Sn 2 AE |