07 Apr 2021 NOC for applying permission for blasting, from Chapparapadavu Panchayath, is yet to be received Payyannur UIDSSMT WSP Sub Dn AEE
06 Mar 2021 NOC for blasting from Chapparapadavu Panchayath is yet not received Payyannur UIDSSMT WSP Sub Dn AEE
24 Feb 2021 Chapparapadavu Panchayath not issued NOC for obtaining permission for blasting Payyannur UIDSSMT WSP Sub Dn AEE
05 Feb 2021 Permission for rock blasting not received Payyannur UIDSSMT WSP Sub Dn AEE
29 Jan 2021 Permission for hard rock blasting is not received Payyannur UIDSSMT WSP Sub Dn AEE
13 Nov 2020 Permission for tree cutting received Payyannur UIDSSMT WSP Sub Dn AEE
30 Jul 2020 Soil investigation has to be conducted Payyannur UIDSSMT WSP Sub Dn AEE
01 Jul 2020 Work order issued. work not started Payyannur UIDSSMT WSP Sub Dn AEE