Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Nov 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
01 Nov 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
27 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
23 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
19 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
18 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
15 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
11 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
07 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 | |
04 Oct 2021 | Work is stopped temporarily. NOC from Panchayath is not obtained to apply permission for hard rock blasting | Payyannur UIDSSMT AE 3 |