- Home
- State Plan- 2017-18-WSS to Payyanur Muni...
State Plan- 2017-18-WSS to Payyanur Municipality-Balance work- Construction of Intake well cum pump house, supply and erection of raw water pump sets and supply and erection of transformers
Project |
State Plan- 2017-18-WSS to Payyanur Municipality-Balance work- Construction of Intake well cum pump house, supply and erection of raw water pump sets and supply and erection of transformers |
Project Code |
KNRGOK1217556 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
4215-01-800-89 |
Description |
This work is for the balance work of WSS to Payyanur municipality. This work include construction of Intake well cum pump house, supply and erection of raw water pump sets and supply and erection of transformers at Kodumkayam in Chapparapadavu Panchayath |
Status |
Dropped |
District |
Kannur |
Executing Office |
Kannur Project Dn |
AS Amount (Rs) |
61000000
|
AS Number |
G.O.(Rt)No. 1040/2017/WRD dated 20/12/2017 |
TS Amount (Rs) |
60000000 |
TS Number |
TS/2019-20/2018/10908 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
60000 |
Capacity in MLD |
14.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Payyanur Municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan- 2017-18-WSS to Payyanur Municipality-Balance work- Construction of Intake well cum pump house, supply and erection of raw water pump sets and supply and erection of transformers |
UIDSSMT WSP Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Feb 2023 |
Work couldn't proceeded due to Public/Panchayath protest hence work is terminated as on 17.11.2022 |
Payyannur UIDSSMT AE 3 |
|
14 Feb 2023 |
Work couldn't proceeded due to Public/Panchayath protest |
Payyannur UIDSSMT AE 3 |
|
10 Feb 2023 |
Work couldn't proceeded due to Public/Panchayath protest |
Payyannur UIDSSMT AE 3 |
|
07 Feb 2023 |
Work couldn't proceeded due to Public/Panchayath protest |
Payyannur UIDSSMT AE 3 |
|
03 Feb 2023 |
Work couldn't proceeded due to Public/Panchayath protest |
Payyannur UIDSSMT AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
29/04/2020 |
Scheduled date of Completion of the Project |
28 Apr 2021 |
Expected date of Completion |
31/12/2022 |
Processing Dates
AS Date |
20 Dec 2017 |
TS Date |
13 Dec 2019 |