Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Apr 2022 Calculation submitted to Railway Division office. Kochi JNURM Projects AE-6
07 Feb 2022 BPCL has permitted for crossing their corridor on 07.02.2022 Kochi WS Project Dn EE
10 Jan 2022 The proposal submitted to BPCL and railway are under process. Contacted both BPCL and railway for follow up. Kochi Project -AEE 3
21 Dec 2021 Meeting with Executive Director, BPCL will be conducted on 21/12/21 at 2pm. Kochi Project -AEE 3
01 Dec 2021 Contacted railway and BPCL for follow up of the proposals submitted Kochi Project -AEE 3
23 Nov 2021 Proposals sent to BPCL and railway as per the decision taken during the meeting conducted by ADM on 2/11/21. Kochi Project -AEE 3
09 Nov 2021 As per the decision in the meeting conducted on 2/11/21, a survey is conducted at the crossing location. The new proposal is under preparation. Kochi Project -AEE 3
05 Nov 2021 Meeting was conducted by ADM on 02/11/21 in which railway and BPCL officials were present. It was directed to submit the proposal for railway crossing and BPCL crossing by push through method Kochi Project -AEE 3
22 Oct 2021 Request sent to District collector for intervening in getting permission from BPCL and railway. Kochi Project -AEE 3
09 Oct 2021 Proposal sent to BPCL for crossing BPCL corridor by push through method along with railway crossing Kochi Project -AEE 3