| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Oct 2024 | Lintel and sunshade concreting completed. | Koothuparambu PH Sn AE | |
| 01 Oct 2024 | Laterite masonry work started. | Koothuparambu PH Sn AE | |
| 24 Sep 2024 | Tie beam and slab concrete completed. | Koothuparambu PH Sn AE | |
| 18 Sep 2024 | Column concrete completed. | Koothuparambu PH Sn AE | |
| 11 Sep 2024 | Plinth beam concrete completed | Koothuparambu PH Sn AE | |
| 05 Sep 2024 | foundation earth filling completed. | Koothuparambu PH Sn AE | |
| 30 Aug 2024 | Foundation concrete completed | Koothuparambu PH Sn AE | |
| 21 Aug 2024 | Site clearance completed. | Koothuparambu PH Sn AE | |