| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Apr 2025 | Work completed. | Koothuparambu PH Sn AE | |
| 27 Mar 2025 | Dismantling of old pump house completed.compound wall work in progress. 583m pipe laid. | Koothuparambu PH Sn AE | |
| 19 Mar 2025 | Dismantling of pumphouse to be done. | Koothuparambu PH Sn AE | |
| 05 Mar 2025 | Pumphouse plastering completed.Painting to be done.530m pipe laid. | Koothuparambu PH Sn AE | |
| 18 Feb 2025 | Pumphouse roof slab concrete completed.348m pipe line laid. | Koothuparambu PH Sn AE | |
| 10 Feb 2025 | Pumphouse roof slab concrete completed.348m pipe line lied. | Koothuparambu PH Sn AE | |
| 31 Jan 2025 | Pumphouse roof slab concrete completed. | Koothuparambu PH Sn AE | |
| 18 Jan 2025 | Construction of pumphouse-55% completed. KSEB LT Line shifted. | Koothuparambu PH Sn AE | |
| 07 Jan 2025 | Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted. | Koothuparambu PH Sn AE | |
| 31 Dec 2024 | Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted. | Koothuparambu PH Sn AE |