KIIFB-Reconstruction of Pumphoue of RWSS to Muzhakunnu-KIIFB - Reconstruction of pump house of RWSS to Muzhakunnu and Supplying and laying of pipe line - Utility shifting for Vallithode Ambayathode road-General Civil Work
Project |
KIIFB-Reconstruction of Pumphoue of RWSS to Muzhakunnu-KIIFB - Reconstruction of pump house of RWSS to Muzhakunnu and Supplying and laying of pipe line - Utility shifting for Vallithode Ambayathode road-General Civil Work |
Project Code |
KNRDEPO022316131 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
KIIFB-Reconstruction of Pumphoue of RWSS to Muzhakunnu-KIIFB - Reconstruction of pump house of RWSS to Muzhakunnu and Supplying and laying of pipe line - Utility shifting for Vallithode Ambayathode road-General Civil Work |
Status |
Completed |
District |
Kannur |
Executing Office |
Koothuparambu PH Sn |
AS Amount (Rs) |
1664000
|
AS Number |
KRFB/1582/2022-SE3(Part3) |
TS Amount (Rs) |
1664000 |
TS Number |
22170/2023-2024 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-Reconstruction of Pumphoue of RWSS to Muzhakunnu-KIIFB - Reconstruction of pump house of RWSS to Muzhakunnu and Supplying and laying of pipe line - Utility shifting for Vallithode Ambayathode road-General Civil Work |
Koothuparambu PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Apr 2025 |
Work completed. |
Koothuparambu PH Sn AE |
|
27 Mar 2025 |
Dismantling of old pump house completed.compound wall work in progress. 583m pipe laid. |
Koothuparambu PH Sn AE |
|
19 Mar 2025 |
Dismantling of pumphouse to be done. |
Koothuparambu PH Sn AE |
|
05 Mar 2025 |
Pumphouse plastering completed.Painting to be done.530m pipe laid. |
Koothuparambu PH Sn AE |
|
18 Feb 2025 |
Pumphouse roof slab concrete completed.348m pipe line laid. |
Koothuparambu PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
25 Feb 2023 |
TS Date |
16 Dec 2023 |