Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Jun 2021 | Package 1 and 2 completed and for Package 3-Road cutting permission applied through ROW for different PWD roads in Kuttanad taluk and PWD given the road restoration charge. Road restoration charge remitted to PWD Alappuzha Division on 5-3-2021 and the stamp paper submitted to the PWD roads subdivision Kuttanad but the agreement is not executed. There is a road cutting ban on PWD roads during election time up to 2-5-2021 and after that the inter connection works in panchayath roads started and the works stopped due to high water table in Kuttanad. | Alappuzha Project Dn AE 3 | |
19 Apr 2021 | Package 1 and 2 completed and package 3-hdpe pipe laying and interconnection works, Road restoration charge remitted to PWD Alappuzha Division for balance pipe laying work. Permission letter issued on 16-03-2021 from PWD Division stating that the road cutting should start only after 2/5/2021 completing the election. | Alappuzha Project Dn AE 3 | |
31 Mar 2021 | Road restoration charge remitted to PWD Alappuzha Division for balance pipe laying work. Permission letter issued on 16-03-2021 from PWD Division stating that the road cutting should start only after 3/5/2021 completing the election. | Alappuzha Project Dn AE 3 | |
20 Mar 2021 | Road restoration charge remitted to PWD Alappuzha Division for balance pipe laying work. Permission letter issued on 16-03-2021 from PWD Division stating that the road cutting should start only after 3/5/2021 completing the election. | Alappuzha Project Dn AE 3 | |
06 Feb 2021 | Road cutting permission applied through ROW for different PWD roads in kuttanad taluk and PWD given the road restoration charge , fund requested to higher office for PWD road restoration charge. Pipeline inter connection work in Muttar panchayath in progress. | Alappuzha Project Dn AE 3 | |
04 Dec 2020 | 4.5LL OHSR at Thakazhy Panchayath commissioned by pumping water using newly erected 15hp pumpsets at WTP Karumadi .The 500mm pipeline out let of tank connected to the existing line before the railway crossing, by this the house holds in that area will get the treated water. At Veliyanad panchayath hdpe pipe laying works and MS/GI pipe culvert crossing done after getting PWD road cutting permisssion on October 2020 and charging and trial running started. In Edathua Panchyath Distribution line charged from the existing OHSR at Edathua Office compound. Thalavady, Muttar and Thakazhy panchayath MS pipe gap filling works are in progress. | Alappuzha Project Dn AE 3 | |
12 Nov 2020 | Balance pipe laying work, charging and commissioning of already laid pipeline in progress, 4.5LL OHSR at thakazhy commissioned by charging water from new pump house constructed at WTP Karumadi. | Alappuzha Project Dn AE 3 | |
30 Jun 2020 | 90 % completed | Alappuzha Project Dn AE 3 |