| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Mar 2021 | 165 FHTCs completed | Aruvikkara HW Dn EE | |
| 11 Mar 2021 | 165 FHTCs completed | Aruvikkara HW Dn EE | |
| 04 Mar 2021 | 145 FHTCs completed | Aruvikkara HW Dn EE | |
| 25 Feb 2021 | 145 FHTCs completed | Aruvikkara HW Dn EE | |
| 14 Feb 2021 | 129 FHTCs completed.Expected date of completion 30.04.2021. | Aruvikkara HW Dn EE | |
| 10 Feb 2021 | 107 nos of FHTCs completed out of 2000. 5700 meters of 90 mm pvc pipe laid. | Aruvikkara HW Dn EE | |
| 09 Feb 2021 | 102 nos of FHTCs completed out of 2000. 5700 meters of 90 mm pvc pipe laid. | Aruvikkara HW Dn EE | |
| 26 Jan 2021 | 43 nos of FHTCs completed out of 2000. 5200 meters of 90 mm pvc pipe laid. | Aruvikkara HW Dn EE | |
| 18 Dec 2020 | 1100 mtrs of 90 mm PVC pipes laid. | Aruvikkara HW Dn EE | |
| 28 Nov 2020 | Factory inspection by CIPET for the first batch over and the pipe (3000m of 90mm PVC) will be supplied by 30.11.2020 and pipe laying work will start from 02.12.2020. | Aruvikkara HW Dn EE |