Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jul 2021 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. Aruvikkara HW Dn EE
01 Jul 2021 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. Aruvikkara HW Dn EE
29 Jun 2021 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. Aruvikkara HW Dn EE
27 Jun 2021 Road crossing work for FHTCs in PWD road progressing Aruvikkara HW Dn EE
21 Jun 2021 Road crossing work for FHTCs in PWD road progressing Aruvikkara HW Dn EE
19 Jun 2021 Road crossing work for FHTCs in PWD road progressing Aruvikkara HW Dn EE
18 Jun 2021 Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road Aruvikkara HW Dn EE
15 Jun 2021 Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road Aruvikkara HW Dn EE
14 Jun 2021 Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road Aruvikkara HW Dn EE
12 Jun 2021 Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road Aruvikkara HW Dn EE