| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jul 2021 | 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 01 Jul 2021 | 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 29 Jun 2021 | 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 27 Jun 2021 | Road crossing work for FHTCs in PWD road progressing | Aruvikkara HW Dn EE | |
| 21 Jun 2021 | Road crossing work for FHTCs in PWD road progressing | Aruvikkara HW Dn EE | |
| 19 Jun 2021 | Road crossing work for FHTCs in PWD road progressing | Aruvikkara HW Dn EE | |
| 18 Jun 2021 | Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road | Aruvikkara HW Dn EE | |
| 15 Jun 2021 | Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road | Aruvikkara HW Dn EE | |
| 14 Jun 2021 | Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road | Aruvikkara HW Dn EE | |
| 12 Jun 2021 | Road crossing work for FHTCs in PWD road progressing in Puthenpalom Venjaramoodu road | Aruvikkara HW Dn EE |