| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Sep 2021 | 845 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted. | Kallara AE | |
| 21 Sep 2021 | 845 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted. | Kallara AE | |
| 20 Sep 2021 | 845 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted. | Kallara AE | |
| 17 Sep 2021 | 845 FHTCs out of 2000 completed and bill for 824 FHTCs submitted. | Kallara AE | |
| 13 Sep 2021 | 834 FHTCs out of 2000 completed and bill for 824 FHTCs submitted. | Kallara AE | |
| 09 Sep 2021 | 834 FHTCs out of 2000 completed and bill for 824 FHTCs submitted. | Kallara AE | |
| 05 Sep 2021 | 834 FHTCs out of 2000 completed and bill for 824 FHTCs submitted. | Kallara AE | |
| 01 Sep 2021 | 793 FHTCs completed out of 2000 | Kallara AE | |
| 31 Aug 2021 | 793 FHTCs completed out of 2000 | Kallara AE | |
| 27 Aug 2021 | 793 FHTCs completed out of 2000 | Kallara AE |