| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Nov 2021 | 1078 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 19 Nov 2021 | 1078 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 18 Nov 2021 | 1078 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 17 Nov 2021 | 1078 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 15 Nov 2021 | 963 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 11 Nov 2021 | 963 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 08 Nov 2021 | 963 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 06 Nov 2021 | 963 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 05 Nov 2021 | 963 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 02 Nov 2021 | 916 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE |