| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Dec 2021 | 1260 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 18 Dec 2021 | 1260 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 15 Dec 2021 | 1235 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 14 Dec 2021 | 1235 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 13 Dec 2021 | 1200 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 13 Dec 2021 | 1160 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 10 Dec 2021 | 1160 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 09 Dec 2021 | 1160 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 08 Dec 2021 | 1160 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE | |
| 07 Dec 2021 | 1160 FHTCs out of 2000 completed and bill for 824 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted | Kallara AE |