Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jan 2022 1455 FHTCs out of 2000 completed and bill for 1455 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
03 Jan 2022 1455 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
01 Jan 2022 1400 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
31 Dec 2021 1400 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
30 Dec 2021 1400 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
29 Dec 2021 1400 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
28 Dec 2021 1360 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
24 Dec 2021 1320 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
23 Dec 2021 1300 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE
22 Dec 2021 1260 FHTCs out of 2000 completed and bill for 1245 FHTCs submitted.Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE