Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Feb 2021 | waiting for road cutting sanction | Thiruvananthapuram Project AE7 | |
01 Feb 2021 | Met ADM, Collectorate and request given for getting emergency road cutting sanction. | Thiruvananthapuram Project AE7 | |
12 Jan 2021 | Paid road restoration fund in PWD and KRFB. Waiting for getting permission for road cutting. | Thiruvananthapuram Project AE7 | |
09 Nov 2020 | got revised road cutting estimate from KRFB and same uploaded in PFMS server in KIIFB for sanctioning road cutting fund from KIIFB | Thiruvananthapuram Project AE7 | |
13 Sep 2020 | Road cutting sanction not obtained from KRFB and PWD road due to deviation in road restoration estimation in the sanctioned TS | Thiruvananthapuram Project AE7 | |
13 Sep 2020 | 500m of 350mm DI K9 pipe supplied. | Thiruvananthapuram Project AE7 | |
12 Aug 2020 | Work not started. | Thiruvananthapuram Project AE7 |