Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Mar 2021 | one percentage completed till date. waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
27 Mar 2021 | one percentage completed till date. waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
25 Mar 2021 | one percentage completed till date. waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
24 Mar 2021 | one percentage completed till date. waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
23 Mar 2021 | waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
22 Mar 2021 | waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
19 Mar 2021 | waiting for road cutting approval | Thiruvananthapuram Project AE7 | |
16 Mar 2021 | minutes of District Coordination Committee of District Collector received. Letter for road cutting request send to PWD and KRFB. waiting for approval | Thiruvananthapuram Project AE7 | |
09 Mar 2021 | minutes of District Coordination Committee of District Collector received. Letter for road cutting request send to PWD and KRFB | Thiruvananthapuram Project AE7 | |
06 Mar 2021 | Waiting for minutes of District Coordination Committee of District Collector. | Thiruvananthapuram Project AE7 |