Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kollam Project HD
Date: 08/03/2021

Work has been completed | 100% Completed

Completed

Kollam Project HD
Date: 05/03/2021

Work in progress | 99% Completed

finishing works

Kollam Project HD
Date: 02/03/2021

Work in progress | 99% Completed

Work is nearly completed

Kollam Project HD
Date: 24/02/2021

Work in progress | 98% Completed

completion work going on

Kollam Project HD
Date: 23/02/2021

Work in progress | 98% Completed

completion work going on

Kollam Project HD
Date: 22/02/2021

Work in progress | 98% Completed

completion work going on

Kollam Project HD
Date: 20/02/2021

Work in progress | 98% Completed

completion work going on

Kollam Project HD
Date: 17/02/2021

Work in progress | 98% Completed

841 meter of pipe laid

Kollam Project HD
Date: 14/02/2021

Work in progress | 97% Completed

CROSSING OVER A HUGE TREE- SLOW PACE WORK

Kollam Project HD
Date: 11/02/2021

Work in progress | 97% Completed

testing of pipes and completion works in progress

Kollam Project Dn AE3
Date: 09/02/2021

Work in progress | 94% Completed

825 metres of pipe laid and tested

Kollam Project Dn AE3
Date: 07/02/2021

Work has started | 94% Completed

825 metres of pipe laid and tested

Kollam Project HD
Date: 06/02/2021

Work has started | 94% Completed

825 metres of pipe laid and tested

Kollam Project HD
Date: 05/02/2021

Work in progress | 94% Completed

825 metres of pipe laid and tested

Kollam Project Dn AE3
Date: 04/02/2021

Work in progress | 94% Completed

825 metres of pipe laid and tested

Kollam Project HD
Date: 03/02/2021

Work in progress | 94% Completed

825 metres of pipe laid and tested

Kollam Project HD
Date: 31/01/2021

Work in progress | 94% Completed

825 metres of pipe laid

Kollam Project HD
Date: 25/01/2021

Work in progress | 94% Completed

825 metres of pipe laid

Kollam Project HD
Date: 08/01/2021

Work in progress | 90% Completed

809.70m of pipe laid .(90% COMPLETED)

Kollam Project HD
Date: 03/01/2021

Work in progress | 72% Completed

594 metre of line laid

Kollam Project HD
Date: 10/12/2020

Work has started | 0% Completed

CIPET completed pipe testing on 4.12.2020 and work to be started immediately after the permission from PWD&KIIFB