| Kollam Project HD |
| Date: 08/03/2021 |
Work has been completed | 100% Completed
Completed
| Kollam Project HD |
| Date: 05/03/2021 |
Work in progress | 99% Completed
finishing works
| Kollam Project HD |
| Date: 02/03/2021 |
Work in progress | 99% Completed
Work is nearly completed
| Kollam Project HD |
| Date: 24/02/2021 |
Work in progress | 98% Completed
completion work going on
| Kollam Project HD |
| Date: 23/02/2021 |
Work in progress | 98% Completed
completion work going on
| Kollam Project HD |
| Date: 22/02/2021 |
Work in progress | 98% Completed
completion work going on
| Kollam Project HD |
| Date: 20/02/2021 |
Work in progress | 98% Completed
completion work going on
| Kollam Project HD |
| Date: 17/02/2021 |
Work in progress | 98% Completed
841 meter of pipe laid
| Kollam Project HD |
| Date: 14/02/2021 |
Work in progress | 97% Completed
CROSSING OVER A HUGE TREE- SLOW PACE WORK
| Kollam Project HD |
| Date: 11/02/2021 |
Work in progress | 97% Completed
testing of pipes and completion works in progress
| Kollam Project Dn AE3 |
| Date: 09/02/2021 |
Work in progress | 94% Completed
825 metres of pipe laid and tested
| Kollam Project Dn AE3 |
| Date: 07/02/2021 |
Work has started | 94% Completed
825 metres of pipe laid and tested
| Kollam Project HD |
| Date: 06/02/2021 |
Work has started | 94% Completed
825 metres of pipe laid and tested
| Kollam Project HD |
| Date: 05/02/2021 |
Work in progress | 94% Completed
825 metres of pipe laid and tested
| Kollam Project Dn AE3 |
| Date: 04/02/2021 |
Work in progress | 94% Completed
825 metres of pipe laid and tested
| Kollam Project HD |
| Date: 03/02/2021 |
Work in progress | 94% Completed
825 metres of pipe laid and tested
| Kollam Project HD |
| Date: 31/01/2021 |
Work in progress | 94% Completed
825 metres of pipe laid
| Kollam Project HD |
| Date: 25/01/2021 |
Work in progress | 94% Completed
825 metres of pipe laid
| Kollam Project HD |
| Date: 08/01/2021 |
Work in progress | 90% Completed
809.70m of pipe laid .(90% COMPLETED)
| Kollam Project HD |
| Date: 03/01/2021 |
Work in progress | 72% Completed
594 metre of line laid
| Kollam Project HD |
| Date: 10/12/2020 |
Work has started | 0% Completed
CIPET completed pipe testing on 4.12.2020 and work to be started immediately after the permission from PWD&KIIFB