Kannur WS Sn AE 2
Date: 04/06/2026

Work has been completed | 100% Completed

Work completed. Final bill Submitted.

Kannur WS Sn AE 2
Date: 29/04/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 17/04/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 08/04/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 24/03/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 06/03/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 25/02/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 16/02/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 20/01/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 05/01/2026

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 27/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 16/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 13/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 09/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 05/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 02/12/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 28/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 24/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 20/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 17/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 13/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 10/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 07/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 03/11/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 30/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 25/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 21/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 15/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 09/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 06/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 03/10/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 29/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 25/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 22/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 18/09/2025

Work in progress | 95% Completed

Site Handed over on 06/09/2025.

Kannur WS Sn AE 2
Date: 15/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 11/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 08/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 04/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 01/09/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 29/08/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 25/08/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 21/08/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 18/08/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 14/08/2025

Work in progress | 95% Completed

86 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 06/08/2025

Work in progress | 77% Completed

70 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 04/08/2025

Work in progress | 77% Completed

70 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 31/07/2025

Work in progress | 77% Completed

70 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 28/07/2025

Work in progress | 77% Completed

70 Nos public tap disconnected out of 90 Nos

Kannur WS Sn AE 2
Date: 26/07/2025

Work in progress | 77% Completed

70 Nos public tap disconnected out of 90 Nos

Kannur WS Sub-Dn - AEE
Date: 30/06/2025

Work in progress | 1% Completed

ONGOING