Thaliparamba WS Dn EE
Date: 13/09/2023

Work has been completed | 100% Completed

pumping main 350mm - 1574.5 m , pumping main 250mm -1942 m , pumping main 90mm PE-2270 m , Transmission main 350 mm - 875 m , Transmission main 350 mm - 482 m

Thaliparamba WS Dn EE
Date: 11/09/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 07/09/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 04/09/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 01/09/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 25/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 21/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 18/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 16/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 10/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 07/08/2023

Work in progress | 90% Completed

PIPE SUPPLY COMPLETED...PUMPING MAIN LAYING WORK COMPLETED ...DISTRIBUTION PIPELINE LAYING ONGOING

Thaliparamba WS Dn EE
Date: 03/08/2023

Work in progress | 63% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 31/07/2023

Work in progress | 63% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 27/07/2023

Work in progress | 63% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 24/07/2023

Work in progress | 63% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 22/07/2023

Work in progress | 63% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 19/07/2023

Work in progress | 62% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 14/07/2023

Work in progress | 62% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 10/07/2023

Work in progress | 62% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 06/07/2023

Work in progress | 61% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 03/07/2023

Work in progress | 61% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 30/06/2023

Work in progress | 60% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 26/06/2023

Work in progress | 60% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 22/06/2023

Work in progress | 18% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 19/06/2023

Work in progress | 17% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 15/06/2023

Work in progress | 16% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 12/06/2023

Work in progress | 16% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 08/06/2023

Work in progress | 15% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 05/06/2023

Work in progress | 14% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 01/06/2023

Work in progress | 13% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 29/05/2023

Work in progress | 12% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 25/05/2023

Work in progress | 11% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 22/05/2023

Work in progress | 10% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 18/05/2023

Work in progress | 10% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 15/05/2023

Work in progress | 5% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied

Thaliparamba WS Dn EE
Date: 11/05/2023

Work in progress | 5% Completed

work started -- 2270 meter 90 PE and 1188 meter 350 DI supplied