Chavara AE
Date: 28/02/2026

Work has been completed | 100% Completed

work completed

Chavara AE
Date: 03/02/2026

Work has been completed | 100% Completed

Pump house construction completed

Chavara AE
Date: 02/02/2026

Work has been completed | 100% Completed

Pump house construction completed

Attached images

img

Chavara AE
Date: 29/01/2026

Work in progress | 92% Completed

Got KSEB Connection.

Chavara AE
Date: 24/01/2026

Work in progress | 60% Completed

Pump house construction road crossing work completed.

Attached images

img

Chavara AE
Date: 20/01/2026

Work in progress | 55% Completed

Road crossing completed

Attached images

img img img