Cheruvathur AE
Date: 01/07/2024

Work in progress | 72% Completed

42000m pipe line laid, 361 FHTCs are given, 173 HTCs are given, 3rd part bill submitted

Cheruvathur AE
Date: 27/06/2024

Work in progress | 71% Completed

42000m pipe line laid, 173FHTCs are given, 350 HTCs are given, 3rd part bill submitted

Cheruvathur AE
Date: 24/06/2024

Work in progress | 71% Completed

42000m pipe line laid, 173FHTCs are given, 350 HTCs are given, 3rd part bill submitted

Cheruvathur AE
Date: 12/06/2024

Work in progress | 71% Completed

42000m pipe line laid, 173FHTCs are given, 350 HTCs are given, 3rd part bill submitted

Cheruvathur AE
Date: 30/05/2024

Work in progress | 68% Completed

34 km pipe line laid, 173FHTCs are given, 350 HTCs are given, 3rd part bill submitted

Cheruvathur AE
Date: 27/05/2024

Work in progress | 67% Completed

33Kms pipe line laid and 155 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 23/04/2024

Work in progress | 67% Completed

33Kms pipe line laid and 155 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 15/04/2024

Work in progress | 67% Completed

33Kms pipe line laid and 155 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 01/04/2024

Work in progress | 65% Completed

33Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 25/03/2024

Work in progress | 64% Completed

33Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 18/03/2024

Work in progress | 63% Completed

33Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 11/03/2024

Work in progress | 63% Completed

33Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 26/02/2024

Work in progress | 63% Completed

33Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 19/02/2024

Work in progress | 61% Completed

30Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 14/02/2024

Work in progress | 60% Completed

30Kms pipe line laid and 25 nos. FHTC given, 260 nos. HTC given

Cheruvathur AE
Date: 05/02/2024

Work in progress | 52% Completed

25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 29/01/2024

Work in progress | 50% Completed

25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 22/01/2024

Work in progress | 49% Completed

25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 15/01/2024

Work in progress | 49% Completed

25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 08/01/2024

Work in progress | 48% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 01/01/2024

Work in progress | 46% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 28/12/2023

Work in progress | 44% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 11/12/2023

Work in progress | 42% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 27/11/2023

Work in progress | 40% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 23/11/2023

Work in progress | 40% Completed

Work in progress . 25Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 20/11/2023

Work in progress | 35% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 16/11/2023

Work in progress | 31% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 13/11/2023

Work in progress | 31% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 02/11/2023

Work in progress | 31% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given, 150 nos. HTC given

Cheruvathur AE
Date: 30/10/2023

Work in progress | 29% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given

Cheruvathur AE
Date: 26/10/2023

Work in progress | 29% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given

Cheruvathur AE
Date: 23/10/2023

Work in progress | 29% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given.

Cheruvathur AE
Date: 19/10/2023

Work in progress | 28% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given.

Cheruvathur AE
Date: 16/10/2023

Work in progress | 28% Completed

Work in progress . 20Kms pipe line laid and 25 nos. FHTC given.

Cheruvathur AE
Date: 11/10/2023

Work in progress | 26% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given

Cheruvathur AE
Date: 07/09/2023

Work in progress | 26% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given

Cheruvathur AE
Date: 05/09/2023

Work in progress | 26% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given

Cheruvathur AE
Date: 26/08/2023

Work in progress | 26% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given

Cheruvathur AE
Date: 23/08/2023

Work in progress | 26% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given

Cheruvathur AE
Date: 18/08/2023

Work in progress | 25% Completed

work in progress . 20Kms pipe line laid and 200nos of HTCs physically given