| Kollam WS Sn 2 - AE |
| Date: 11/01/2024 |
Work has been completed | 100% Completed
Work completed on 11/1/24. . Time of extension up to 15/1/2024 already got .
| Kollam WS Sn 2 - AE |
| Date: 09/01/2024 |
Work in progress | 99% Completed
Road crossing permission got and interconnection done. Replacing chocked connection are progressing.
| Kollam WS Sn 2 - AE |
| Date: 06/01/2024 |
Work in progress | 76% Completed
Balance interconnection works will arrange today night 8 pm( heavy traficable area)
| Kollam WS Sn 2 - AE |
| Date: 03/01/2024 |
Work in progress | 76% Completed
Agreement executing by NH PWD Road subdivision under process.
| Kollam WS Sn 2 - AE |
| Date: 29/12/2023 |
Work in progress | 76% Completed
Agreement executing for getting permission for tar cutting under process
| Kollam WS Sn 2 - AE |
| Date: 26/12/2023 |
Work in progress | 76% Completed
Agreement executing by NH authorities for getting tar cutting sanction under process
| Kollam WS Sn 2 - AE |
| Date: 12/12/2023 |
Work in progress | 76% Completed
Demand notice from NH Dept. got and submitted to higher office for fund request.
| Kollam WS Sn 2 - AE |
| Date: 08/12/2023 |
Work in progress | 76% Completed
Demand notice from NH Dept. got and submitted to higher office for fund request.
| Kollam WS Sn 2 - AE |
| Date: 04/12/2023 |
Work in progress | 76% Completed
Demand notice from NH Dept. got and submitted to higher office for fund request.
| Kollam WS Sn 2 - AE |
| Date: 30/11/2023 |
Work in progress | 76% Completed
Demand notice from NH Dept. got and submitted to higher office for fund request
| Kollam WS Sn 2 - AE |
| Date: 27/11/2023 |
Work in progress | 76% Completed
Demand notice from NH Dept. got and submitted to higher office for fund request.
| Kollam WS Sn 2 - AE |
| Date: 10/11/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA and Kollam corporation.
| Kollam WS Sn 2 - AE |
| Date: 06/11/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA and Kollam corporation.
| Kollam WS Sn 2 - AE |
| Date: 01/11/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 25/10/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 16/10/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 09/10/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 03/10/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 25/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA.
| Kollam WS Sn 2 - AE |
| Date: 21/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office.
| Kollam WS Sn 2 - AE |
| Date: 18/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office.
| Kollam WS Sn 2 - AE |
| Date: 12/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office.
| Kollam WS Sn 2 - AE |
| Date: 08/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office.
| Kollam WS Sn 2 - AE |
| Date: 04/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office.
| Kollam WS Sn 2 - AE |
| Date: 01/09/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by higher office
| Kollam WS Sn 2 - AE |
| Date: 24/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted byo higher office
| Kollam WS Sn 2 - AE |
| Date: 18/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted byo higher office
| Kollam WS Sn 2 - AE |
| Date: 15/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor
| Kollam WS Sn 2 - AE |
| Date: 11/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor
| Kollam WS Sn 2 - AE |
| Date: 07/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor
| Kollam WS Sn 2 - AE |
| Date: 02/08/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor
| Kollam WS Sn 2 - AE |
| Date: 29/07/2023 |
Work in progress | 76% Completed
Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted.
| Kollam WS Sn 2 - AE |
| Date: 27/07/2023 |
Work in progress | 76% Completed
Pipe laying work completed and interconnection work pending due to delay for getting road cutting sanction
| Kollam WS Sn 2 - AE |
| Date: 22/07/2023 |
Work in progress | 76% Completed
Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction
| Kollam WS Sn 2 - AE |
| Date: 17/07/2023 |
Work in progress | 76% Completed
Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction
| Kollam WS Sn 2 - AE |
| Date: 13/07/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 28/06/2023 |
Work in progress | 0% Completed
tested pipe not get
| Kollam WS Sn 2 - AE |
| Date: 24/06/2023 |
Work has started | 0% Completed
LOA issued, Pipe testing process under progress agreement executed.