| Kollam WS Sn 2 - AE |
| Date: 01/04/2024 |
Work has been completed | 100% Completed
KSEB connection got on 27/3/24 and pump erection and interconnection works completed on 30/3/24
| Kollam WS Sn 2 - AE |
| Date: 25/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing,
| Kollam WS Sn 2 - AE |
| Date: 21/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted.
| Kollam WS Sn 2 - AE |
| Date: 15/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted.
| Kollam WS Sn 2 - AE |
| Date: 11/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing, Time of extension recommendation submitted.
| Kollam WS Sn 2 - AE |
| Date: 06/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing
| Kollam WS Sn 2 - AE |
| Date: 01/03/2024 |
Work in progress | 70% Completed
KSEB connection not get till date, follow up action is ongoing
| Kollam WS Sn 2 - AE |
| Date: 27/02/2024 |
Work in progress | 70% Completed
Pump house construction work completed. Pump set , and connected materials are received. Errection and commissioning Pending due to electricity connection from KSEB not get .
| Kollam WS Sub Dn - AEE |
| Date: 21/02/2024 |
Work in progress | 36% Completed
Pump house construction work completed. Pump set , and connected materials are received. Pending for getting electricity connection.
| Kollam WS Sn 2 - AE |
| Date: 17/02/2024 |
Work in progress | 20% Completed
Pump house construction work in progress and pump set received.
| Kollam WS Sn 2 - AE |
| Date: 13/02/2024 |
Work in progress | 1% Completed
Site handed over and work started
| Kollam WS Sn 2 - AE |
| Date: 06/02/2024 |
Work in progress | 0% Completed
Site handover cannot done because no SHO proforma uploaded by the contractor.
| Kollam WS Sub Dn - AEE |
| Date: 05/02/2024 |
Work has started | 0% Completed
AGREEMENT EXECUTED ON 03.02.24