Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode PH Dn EE
Date: 30/06/2024

Work has been completed | 100% Completed

completed

Kozhikode PH Dn EE
Date: 25/06/2024

Work in progress | 97% Completed

Almost completed. Due to heavy traffic and public protestant Changing connection is pending

Kozhikode PH Dn EE
Date: 24/06/2024

Work in progress | 97% Completed

Almost completed. Due to heavy traffic and public protestant Changing connection is pending

Kozhikode PH Dn EE
Date: 14/06/2024

Work in progress | 97% Completed

pipe laid-1.94km

Kozhikode PH Dn EE
Date: 21/04/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 55% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 39% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 05/03/2024

Work has started | 0% Completed

PWD road cutting permission received on 04-03-2024.

Kozhikode PH Dn EE
Date: 14/02/2024

Work has started | 0% Completed

WORK NOT STARTED

Kozhikode PH Dn EE
Date: 27/01/2024

Work has started | 0% Completed

Work order issued

Kozhikode PH Dn EE
Date: 12/01/2024

Work has started | 0% Completed

Work order issued