Kollam WS Sn 2 - AE
Date: 13/01/2025

Work has been completed | 100% Completed

WORK COMPLETED AND FINAL BILL SUBMITTED

Kollam WS Sn 2 - AE
Date: 06/01/2025

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 01/01/2025

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 26/12/2024

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 23/12/2024

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 21/12/2024

Work in progress | 90% Completed

2698.70 meter pipe laid out of 3250 meter and work ongoing

Kollam WS Sn 2 - AE
Date: 16/12/2024

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 09/12/2024

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 05/12/2024

Work in progress | 90% Completed

Work started on 2/12/2024 and progressing (pipe laying completed)

Kollam WS Sn 2 - AE
Date: 02/12/2024

Work in progress | 55% Completed

Work started on 2/12/2024 and progressing

Kollam WS Sn 2 - AE
Date: 30/11/2024

Work in progress | 0% Completed

Pipe and specials ordered.

Kollam WS Sn 2 - AE
Date: 20/11/2024

Work has started | 0% Completed

Pipe and specials ordered.

Kollam WS Sn 2 - AE
Date: 14/11/2024

Work in progress | 0% Completed

Pipe and specials ordered.

Kollam WS Sn 2 - AE
Date: 11/11/2024

Work has started | 0% Completed

Work arranged

Kollam WS Sn 2 - AE
Date: 05/11/2024

Work has started | 0% Completed

Work arranged

Kollam WS Sn 2 - AE
Date: 02/11/2024

Work has started | 0% Completed

Work arranged

Kollam WS Sn 2 - AE
Date: 29/10/2024

Work has started | 0% Completed

Work arranged