Kollam Project Dn EE
Date: 18/05/2023

Work has been completed | 100% Completed

Work completed

Kollam Project Dn EE
Date: 19/04/2023

Work in progress | 93% Completed

BM laying work completed 86%

Attached images

img img

Kollam Project Dn EE
Date: 27/02/2023

Work in progress | 84% Completed

Sand piling work , GSB and WMM laying completed

Attached images

img img img

Kollam Project Dn EE
Date: 26/02/2023

Work in progress | 76% Completed

Sand piling, GSB, and WMM laid for a length of 950m

Attached images

img img img

Kollam Project Dn EE
Date: 25/02/2023

Work in progress | 70% Completed

Sand piling, GSB, and WMM laid for a length of 910m.

Attached images

img img img img img img

Kollam Project Dn EE
Date: 24/02/2023

Work in progress | 51% Completed

Sand piling, GSB, and WMM laid for a length of 615m.

Attached images

img img img img img img

Kollam Project Dn EE
Date: 23/02/2023

Work in progress | 20% Completed

Sand piling, GSB, and WMM laid for a length of 615m.

Attached images

img img img img img img img img

Kollam Project Dn EE
Date: 22/02/2023

Work in progress | 16% Completed

Sand piling, GSB, and WMM laid for a length of 400m.

Attached images

img img img img img img img img img img img img img img img img

Kollam Project Dn EE
Date: 21/02/2023

Work in progress | 15% Completed

Sand piling, GSB, and WMM laid for a length of 250m.

Attached images

img

Kollam Project Dn EE
Date: 20/02/2023

Work in progress | 10% Completed

Sand piling, GSB, and WMM laid for a length of 120m.

Attached images

img img