| Kottakkal PH Sn AE |
| Date: 11/05/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 10/04/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 26/03/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 16/03/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 12/03/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 07/03/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 02/03/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 27/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 23/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 18/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 11/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 06/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 02/02/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 29/01/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 17/01/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 12/01/2026 |
Work in progress | 31% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 09/01/2026 |
Work in progress | 31% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 29/12/2025 |
Work in progress | 31% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 24/12/2025 |
Work in progress | 31% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 22/12/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 15/12/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 28/11/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 25/11/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 17/11/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 05/11/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 29/10/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 23/10/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 17/10/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 10/10/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 06/10/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 29/09/2025 |
Work in progress | 30% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 23/09/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 15/09/2025 |
Work in progress | 30% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 11/09/2025 |
| Kottakkal PH Sn AE |
| Date: 21/08/2025 |
Work in progress | 25% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 04/08/2025 |
| Kottakkal PH Sn AE |
| Date: 17/07/2025 |
Work in progress | 22% Completed
work in progress
| Edappal PH Dn EE |
| Date: 14/07/2025 |
Work in progress | 22% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 05/07/2025 |
Work in progress | 22% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 25/06/2025 |
Work in progress | 20% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 19/06/2025 |
Work in progress | 20% Completed
20% completed Work in progress
| Edappal PH Dn EE |
| Date: 12/06/2025 |
Work in progress | 20% Completed
20% completed . Work in progress
| Kottakkal PH Sn AE |
| Date: 10/06/2025 |
Work in progress | 20% Completed
20% completed . Work in progress
| Edappal PH Dn EE |
| Date: 02/06/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 12/05/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 28/04/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 29/03/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 24/03/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 13/03/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 25/02/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 19/02/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 07/02/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 29/01/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Edappal PH Dn EE |
| Date: 24/01/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Kottakkal PH Sn AE |
| Date: 14/01/2025 |
Work in progress | 15% Completed
First level columns (40 no.s) concreting completed
| Kottakkal PH Sn AE |
| Date: 31/12/2024 |
Work in progress | 11% Completed
WORK IN PROGRESS.
| Edappal PH Dn EE |
| Date: 21/12/2024 |
Work in progress | 10% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 17/12/2024 |
Work in progress | 10% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 09/12/2024 |
Work in progress | 10% Completed
CONCRETING OF ALL FOOTINGS (SAY 40) WERE COMPLETED.
| Edappal PH Dn EE |
| Date: 04/12/2024 |
Work in progress | 10% Completed
CONCRETING OF ALL FOOTINGS (SAY 40) WERE COMPLETED.
| Edappal PH Dn EE |
| Date: 30/11/2024 |
Work in progress | 10% Completed
CONCRETING OF ALL FOOTINGS (SAY 40) WERE COMPLETED.
| Kottakkal PH Sn AE |
| Date: 25/11/2024 |
Work in progress | 10% Completed
CONCRETING OF ALL FOOTINGS (SAY 40) WERE COMPLETED
| Edappal PH Dn EE |
| Date: 22/11/2024 |
Work in progress | 8% Completed
Work in progress.
| Edappal PH Dn EE |
| Date: 18/11/2024 |
Work in progress | 8% Completed
Work in progress.
| Kottakkal PH Sn AE |
| Date: 11/11/2024 |
Work in progress | 8% Completed
Work in progress
| Edappal PH Dn EE |
| Date: 05/11/2024 |
Work in progress | 8% Completed
Work in progress.
| Kottakkal PH Sn AE |
| Date: 29/10/2024 |
Work in progress | 8% Completed
Work in progress
| Kottakkal PH Sn AE |
| Date: 24/10/2024 |
Work in progress | 8% Completed
Excavation for footings were completely finished
| Kottakkal PH Sn AE |
| Date: 21/10/2024 |
Work in progress | 7% Completed
Excavation for balance footings is going on.
| Kottakkal PH Sn AE |
| Date: 16/10/2024 |
Work in progress | 6% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 07/10/2024 |
Work in progress | 6% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 28/09/2024 |
Work in progress | 6% Completed
Work in Progress
| Kottakkal PH Sn AE |
| Date: 26/09/2024 |
Work in progress | 6% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 19/09/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 13/09/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 07/09/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 31/08/2024 |
Work in progress | 5% Completed
shifting of pipeline work
| Kottakkal PH Sn AE |
| Date: 23/08/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 17/08/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 14/08/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 26/07/2024 |
Work in progress | 5% Completed
ongoing
| Kottakkal PH Sn AE |
| Date: 05/07/2024 |
Work in progress | 5% Completed
work ongoing
| Kottakkal PH Sn AE |
| Date: 28/06/2024 |
Work in progress | 5% Completed
work ongoing
| Kottakkal PH Sn AE |
| Date: 24/06/2024 |
Work in progress | 5% Completed
work ongoing
| Kottakkal PH Sn AE |
| Date: 18/06/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 10/06/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 03/06/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 30/05/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 27/05/2024 |
Work in progress | 5% Completed
work in progress
| Kottakkal PH Sn AE |
| Date: 21/05/2024 |
| Kottakkal PH Sn AE |
| Date: 13/05/2024 |
| Kottakkal PH Sn AE |
| Date: 06/05/2024 |
| Kottakkal PH Sn AE |
| Date: 02/05/2024 |
| Kottakkal PH Sn AE |
| Date: 29/04/2024 |
| Kottakkal PH Sn AE |
| Date: 23/04/2024 |
| Kottakkal PH Sn AE |
| Date: 20/04/2024 |
| Kottakkal PH Sn AE |
| Date: 15/04/2024 |
| Kottakkal PH Sn AE |
| Date: 11/04/2024 |
Work in progress | 3% Completed
Foundation footing work in progress.
| Kottakkal PH Sn AE |
| Date: 06/04/2024 |
| Kottakkal PH Sn AE |
| Date: 30/03/2024 |
Work in progress | 2% Completed
Bar bending for Footing work in progress
| Kottakkal PH Sn AE |
| Date: 26/03/2024 |
| Kottakkal PH Sn AE |
| Date: 18/03/2024 |
Work in progress | 1% Completed
excavation of foundation work in progress
| Kottakkal PH Sn AE |
| Date: 12/03/2024 |
| Kottakkal PH Sn AE |
| Date: 06/03/2024 |
| Kottakkal PH Sn AE |
| Date: 02/03/2024 |
Work in progress | 1% Completed
Setting out work started
| Kottakkal PH Sn AE |
| Date: 26/02/2024 |
Work has started | 0% Completed
site clearing work completed
| Kottakkal PH Sn AE |
| Date: 21/02/2024 |
Work has started | 0% Completed
site clearing work completed
| Kottakkal PH Sn AE |
| Date: 15/02/2024 |
Work has started | 0% Completed
site clearing work completed
| Kottakkal PH Sn AE |
| Date: 12/02/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 08/02/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 05/02/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 01/02/2024 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 29/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 25/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 22/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 19/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 15/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 12/01/2024 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 09/01/2024 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 06/01/2024 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 04/01/2024 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 01/01/2024 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 29/12/2023 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 26/12/2023 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 23/12/2023 |
Work has started | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 21/12/2023 |
Work in progress | 0% Completed
Site clearing work completed.
| Kottakkal PH Sn AE |
| Date: 18/12/2023 |
Work in progress | 0% Completed
Site clearing work in progress.
| Kottakkal PH Sn AE |
| Date: 15/12/2023 |
Work in progress | 0% Completed
Site clearing work started.
| Kottakkal PH Sn AE |
| Date: 14/12/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 05/12/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 02/12/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 28/11/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 25/11/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 22/11/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 18/11/2023 |
Work has started | 0% Completed
Not started
| Kottakkal PH Sn AE |
| Date: 15/11/2023 |
Work has started | 0% Completed
Not Started