Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Nettoor SRI Circle Director
Date: 29/11/2022

Work has been completed | 100% Completed

Completed.

Nettoor SRI Circle Director
Date: 05/03/2022

Work has been completed | 100% Completed

Supply and Installation completed

Nettoor SRI Circle Director
Date: 25/02/2022

Work in progress | 90% Completed

Supply completed. Installation in Progress

Nettoor SRI Circle Director
Date: 17/02/2022

Work in progress | 85% Completed

Supply completed. Installation in progress

Nettoor SRI Circle Director
Date: 10/02/2022

Work in progress | 80% Completed

supply completed. Installation started

Nettoor SRI Circle Director
Date: 03/02/2022

Work in progress | 50% Completed

Supply and Installation in Progress

Nettoor SRI Circle Director
Date: 27/01/2022

Work in progress | 5% Completed

Agreement Executed. Supply started

Nettoor SRI Circle Director
Date: 04/01/2022

Work in progress | 1% Completed

selection notice issued on 29/12/21. Execution of agreement under process