| Kozhikode PH Dn EE |
| Date: 22/01/2025 |
Work in progress | 100% Completed
95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted
| Kozhikode PH Dn EE |
| Date: 10/01/2025 |
Work in progress | 100% Completed
95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted
| Kozhikode PH Dn EE |
| Date: 03/01/2025 |
Work in progress | 100% Completed
95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted
| Kozhikode PH Dn EE |
| Date: 12/12/2024 |
Work has been completed | 100% Completed
95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted.
| Kozhikode PH Dn EE |
| Date: 07/12/2024 |
Work has been completed | 100% Completed
95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted.
| Kozhikode PH Dn EE |
| Date: 02/12/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 27/11/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 22/11/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 20/11/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 13/11/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 11/11/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 29/10/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallal to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 25/10/2024 |
Work in progress | 95% Completed
95 % completed 67m pipe line to be laid parallal to railway. Permission not received. Discussion can be done to change work to AMRUT 2
| Kozhikode PH Dn EE |
| Date: 28/09/2024 |
Work in progress | 95% Completed
Railway permission for 67 m pending ,PWD -NH permission pending
| Kozhikode PH Dn EE |
| Date: 19/09/2024 |
Work in progress | 95% Completed
Railway permission for 67 m pending ,PWD -NH permission pending
| Kozhikode PH Dn EE |
| Date: 10/09/2024 |
Work in progress | 95% Completed
Railway permission for 72 m pending ,PWD -NH permission pending
| Kozhikode PH Dn EE |
| Date: 21/08/2024 |
Work in progress | 95% Completed
Railway permission for 72 m pending, PWD - NH permission pending
| Kozhikode PH Dn EE |
| Date: 27/06/2024 |
Work in progress | 90% Completed
on going
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 80% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 35% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 30% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 28% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 25% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 11/01/2024 |
Work in progress | 23% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work in progress | 20% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work in progress | 18% Completed
Pipe Supplyed
| Kozhikode PH Dn EE |
| Date: 09/11/2023 |
Work in progress | 13% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work in progress | 10% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 17/10/2023 |
Work in progress | 5% Completed
Pipe Supplied
| Kozhikode PH Dn EE |
| Date: 14/09/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 05/09/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 17/08/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 08/08/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 24/07/2023 |
Work has started | 0% Completed
Site Handed Over. Work Not Yet Started
| Kozhikode PH Dn EE |
| Date: 12/07/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 30/06/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 20/06/2023 |
Work has started | 0% Completed
Work not started
| Kozhikode PH Dn EE |
| Date: 13/06/2023 |
Work has started | 0% Completed
LOA Submitted for Approval
| Kozhikode PH Dn EE |
| Date: 05/06/2023 |
Work has started | 0% Completed
LOA Submitted for Approval
| Kozhikode PH Dn EE |
| Date: 01/06/2023 |
Work has started | 0% Completed
LOA Submitted for Approval