Kozhikode PH Dn EE
Date: 22/01/2025

Work in progress | 100% Completed

95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted

Kozhikode PH Dn EE
Date: 10/01/2025

Work in progress | 100% Completed

95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted

Kozhikode PH Dn EE
Date: 03/01/2025

Work in progress | 100% Completed

95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted

Kozhikode PH Dn EE
Date: 12/12/2024

Work has been completed | 100% Completed

95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted.

Kozhikode PH Dn EE
Date: 07/12/2024

Work has been completed | 100% Completed

95 % completed. 72m pipe line to be laid parallal to railway & crossing. Permission not received. Request for short closing on tranfer the remaining work to Amrut 2 were submitted.

Kozhikode PH Dn EE
Date: 02/12/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 27/11/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 22/11/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 20/11/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 13/11/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 11/11/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallel to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 29/10/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallal to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 25/10/2024

Work in progress | 95% Completed

95 % completed 67m pipe line to be laid parallal to railway. Permission not received. Discussion can be done to change work to AMRUT 2

Kozhikode PH Dn EE
Date: 28/09/2024

Work in progress | 95% Completed

Railway permission for 67 m pending ,PWD -NH permission pending

Kozhikode PH Dn EE
Date: 19/09/2024

Work in progress | 95% Completed

Railway permission for 67 m pending ,PWD -NH permission pending

Kozhikode PH Dn EE
Date: 10/09/2024

Work in progress | 95% Completed

Railway permission for 72 m pending ,PWD -NH permission pending

Kozhikode PH Dn EE
Date: 21/08/2024

Work in progress | 95% Completed

Railway permission for 72 m pending, PWD - NH permission pending

Kozhikode PH Dn EE
Date: 27/06/2024

Work in progress | 90% Completed

on going

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 80% Completed

Work in progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 35% Completed

Work in progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 30% Completed

Work in progress

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 28% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 25% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 11/01/2024

Work in progress | 23% Completed

Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work in progress | 20% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/11/2023

Work in progress | 18% Completed

Pipe Supplyed

Kozhikode PH Dn EE
Date: 09/11/2023

Work in progress | 13% Completed

Work in progress

Kozhikode PH Dn EE
Date: 28/10/2023

Work in progress | 10% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 17/10/2023

Work in progress | 5% Completed

Pipe Supplied

Kozhikode PH Dn EE
Date: 14/09/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 05/09/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 17/08/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 08/08/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 24/07/2023

Work has started | 0% Completed

Site Handed Over. Work Not Yet Started

Kozhikode PH Dn EE
Date: 12/07/2023

Work has started | 0% Completed

Work not started

Kozhikode PH Dn EE
Date: 30/06/2023

Work has started | 0% Completed

Work not started

Kozhikode PH Dn EE
Date: 20/06/2023

Work has started | 0% Completed

Work not started

Kozhikode PH Dn EE
Date: 13/06/2023

Work has started | 0% Completed

LOA Submitted for Approval

Kozhikode PH Dn EE
Date: 05/06/2023

Work has started | 0% Completed

LOA Submitted for Approval

Kozhikode PH Dn EE
Date: 01/06/2023

Work has started | 0% Completed

LOA Submitted for Approval