All updates

Sasthamcotta WS Sn 2 HW - AE
Date: 24/06/2024

Work has been completed | 100% Completed

Deposit work - Mynagappally grama panchayat - RWSS to Mynagappally - Disconnection of public tap in Mynagappally grama panchayat.

Sasthamcotta WS Sn 2 HW - AE
Date: 04/08/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 24/07/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 12/07/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 24/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 20/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 12/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 09/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 06/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 03/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 01/06/2023

Work has been completed | 100% Completed

Work completed.

Sasthamcotta WS Sn 2 HW - AE
Date: 29/05/2023

Work in progress | 65% Completed

Work under progress. 480nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 25/05/2023

Work in progress | 65% Completed

Work under progress. 480nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 22/05/2023

Work in progress | 65% Completed

Work under progress. 450 nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 17/05/2023

Work in progress | 61% Completed

Work under progress. 410 nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 15/05/2023

Work in progress | 60% Completed

Work under progree. 300 nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 08/05/2023

Work in progress | 60% Completed

Work under progress. 300 nos of public taps are disconnected till now.

Sasthamcotta WS Sn 2 HW - AE
Date: 03/05/2023

Work in progress | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 27/04/2023

Work has started | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 17/04/2023

Work has started | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 10/04/2023

Work in progress | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 02/04/2023

Work has started | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 31/03/2023

Work has started | 0% Completed

work tendered

Sasthamcotta WS Sn 2 HW - AE
Date: 25/03/2023

Work has started | 0% Completed

Work tendered.

Sasthamcotta WS Sn 2 HW - AE
Date: 24/03/2023

Work has started | 0% Completed

Work tendered.