Koothuparamba Proj AE 2
Date: 31/10/2023

Work has been completed | 100% Completed

Work completed and 700 FHTC given 31.07.2023

Koothuparamba Proj AE 2
Date: 06/10/2023

Work has been completed | 100% Completed

Work completed

Koothuparamba Proj AE 2
Date: 10/08/2023

Work has been completed | 100% Completed

Work completed

Koothuparamba Proj AE 2
Date: 31/07/2023

Work has been completed | 100% Completed

Work completed

Koothuparamba Proj AE 2
Date: 26/07/2023

Work in progress | 92% Completed

Out of 700no FHTCs ,610nos given

Koothuparamba Proj AE 2
Date: 19/07/2023

Work in progress | 92% Completed

Out of 700no FHTCs ,600nos given

Koothuparamba Proj AE 2
Date: 14/07/2023

Work in progress | 91% Completed

Out of 700no FHTCs ,550nos given

Koothuparamba Proj AE 2
Date: 11/07/2023

Work in progress | 89% Completed

Out of 700no FHTCs ,500nos given

Koothuparamba Proj AE 2
Date: 05/07/2023

Work in progress | 85% Completed

Work in progress 65000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 30/06/2023

Work in progress | 80% Completed

Work in progress 64000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 23/06/2023

Work in progress | 79% Completed

Work in progress 63100m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 19/06/2023

Work in progress | 79% Completed

Work in progress 63000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 12/06/2023

Work in progress | 78% Completed

Work in progress 62500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 06/06/2023

Work in progress | 78% Completed

Work in progress 62000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 01/06/2023

Work in progress | 78% Completed

Work in progress 61000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 25/05/2023

Work in progress | 78% Completed

Work in progress 60500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed

Koothuparamba Proj AE 2
Date: 22/05/2023

Work in progress | 77% Completed

Work in progress, 60000m pipe laid, Interconnection and charging work for already laid line in progress. HTC 450nos completed

Koothuparamba Proj AE 2
Date: 17/05/2023

Work in progress | 77% Completed

Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 300nos completed

Koothuparamba Proj AE 2
Date: 10/05/2023

Work in progress | 76% Completed

Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 270nos completed

Koothuparamba Proj AE 2
Date: 04/05/2023

Work in progress | 76% Completed

Work in progress 57200m pipe laid Interconnection and charging work for already laid line in progress. HTC 250nos completed

Koothuparamba Proj AE 2
Date: 28/04/2023

Work in progress | 75% Completed

Work in progress 56800m pipe laid Interconnection and charging work for already laid line in progress. HTC 200nos completed

Koothuparamba Proj AE 2
Date: 24/04/2023

Work in progress | 75% Completed

Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 172nos completed

Koothuparamba Proj AE 2
Date: 18/04/2023

Work in progress | 74% Completed

Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 150nos completed

Koothuparamba Proj AE 2
Date: 10/04/2023

Work in progress | 74% Completed

Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 05/04/2023

Work in progress | 74% Completed

Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. HTC 100nos completed

Koothuparamba Proj AE 2
Date: 30/03/2023

Work in progress | 73% Completed

Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. second and part bill submitted

Koothuparamba Proj AE 2
Date: 18/03/2023

Work in progress | 73% Completed

Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progres

Koothuparamba Proj AE 2
Date: 02/03/2023

Work in progress | 72% Completed

Work in progress ,Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 01/03/2023

Work in progress | 71% Completed

Work in progress ,Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 27/02/2023

Work in progress | 71% Completed

Work in progress 55890m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 23/02/2023

Work in progress | 70% Completed

Work in progress 55850m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 20/02/2023

Work in progress | 70% Completed

Work in progress 55800m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 17/02/2023

Work in progress | 69% Completed

Work in progress 55700m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 15/02/2023

Work in progress | 68% Completed

Work in progress 55500m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 10/02/2023

Work in progress | 68% Completed

Work in progress 55300m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 08/02/2023

Work in progress | 67% Completed

Work in progress 55000m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 01/02/2023

Work in progress | 67% Completed

Work in progress 54700m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 28/01/2023

Work in progress | 66% Completed

Work in progress 54600m pipe laid Interconnection and charging work for already laid line in progress

Koothuparamba Proj AE 2
Date: 25/01/2023

Work in progress | 65% Completed

Work in progress 54300m pipe laid Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 23/01/2023

Work in progress | 65% Completed

Work in progress 54100m pipe laid Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 19/01/2023

Work in progress | 65% Completed

Work in progress 54000m pipe laid Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 18/01/2023

Work in progress | 55% Completed

Work in progress 52500m pipe laid Interconnection and charging work for already laid line in progress.

Attached images

img img img

Koothuparamba Proj AE 2
Date: 16/01/2023

Work in progress | 54% Completed

Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 13/01/2023

Work in progress | 54% Completed

Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 11/01/2023

Work in progress | 53% Completed

Interconnection and charging work for already laid line in progress.

Koothuparamba Proj AE 2
Date: 10/01/2023

Work in progress | 52% Completed

Work in progress 52000m pipe laid

Koothuparamba Proj AE 2
Date: 08/01/2023

Work in progress | 50% Completed

Work in progress 50250m pipe laid

Koothuparamba Proj AE 2
Date: 06/01/2023

Work in progress | 47% Completed

Work in progress 48100m pipe laid

Koothuparamba Proj AE 2
Date: 31/12/2022

Work in progress | 45% Completed

Work in progress 35600m pipe laid and pressure test for Pipe is in progress

Koothuparamba Proj AE 2
Date: 29/12/2022

Work in progress | 41% Completed

Work in progress 35000m pipe laid and pressure test for Pipe is in progress

Koothuparamba Proj AE 2
Date: 28/12/2022

Work in progress | 40% Completed

work in progress 35000m pipe laid

Koothuparamba Proj AE 2
Date: 17/12/2022

Work in progress | 38% Completed

Work in progress 30000 m pipe laid

Koothuparamba Proj AE 2
Date: 30/11/2022

Work in progress | 35% Completed

Work in progress 26200 m pipe laid

Koothuparamba Proj AE 2
Date: 23/11/2022

Work in progress | 34% Completed

34 % of work completed 25000 m pipe laid

Koothuparamba Proj AE 2
Date: 19/11/2022

Work in progress | 33% Completed

Work in progress.24325m pipe laid

Koothuparamba Proj AE 2
Date: 14/11/2022

Work in progress | 33% Completed

Work in progress.24300m pipe laid. DI pipe laying completed.

Koothuparamba Proj AE 2
Date: 11/11/2022

Work in progress | 33% Completed

Work in progress.22500m pipe laid

Koothuparamba Proj AE 2
Date: 02/11/2022

Work in progress | 31% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.17500m pipe laid

Koothuparamba Proj AE 2
Date: 27/10/2022

Work in progress | 30% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.16600m pipe laid

Koothuparamba Proj AE 2
Date: 24/10/2022

Work in progress | 30% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.165000m pipe laid

Koothuparamba Proj AE 2
Date: 21/10/2022

Work in progress | 29% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.16000m pipe laid View all updates

Koothuparamba Proj AE 2
Date: 17/10/2022

Work in progress | 28% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.14000m pipe laid

Koothuparamba Proj AE 2
Date: 13/10/2022

Work in progress | 27% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.13000m pipe laid

Koothuparamba Proj AE 2
Date: 10/10/2022

Work in progress | 26% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.12000m pipe laid

Koothuparamba Proj AE 2
Date: 06/10/2022

Work in progress | 25% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.9000m pipe laid

Koothuparamba Proj AE 2
Date: 30/09/2022

Work in progress | 24% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.8500m pipe laid

Koothuparamba Proj AE 2
Date: 27/09/2022

Work in progress | 23% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.8000m pipe laid

Koothuparamba Proj AE 2
Date: 20/09/2022

Work in progress | 22% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.8000m pipe laid

Koothuparamba Proj AE 2
Date: 12/09/2022

Work in progress | 20% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.7000m pipe laid

Koothuparamba Proj AE 2
Date: 05/09/2022

Work in progress | 19% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.5800m pipe laid

Koothuparamba Proj AE 2
Date: 30/08/2022

Work in progress | 18% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.5800m pipe laid

Koothuparamba Proj AE 2
Date: 27/08/2022

Work in progress | 17% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.5700m pipe laid

Koothuparamba Proj AE 2
Date: 24/08/2022

Work in progress | 17% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.5500m pipe laid

Koothuparamba Proj AE 2
Date: 20/08/2022

Work in progress | 16% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.4500m pipe laid

Koothuparamba Proj AE 2
Date: 16/08/2022

Work in progress | 15% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.4000m pipe laid

Koothuparamba Proj AE 2
Date: 10/08/2022

Work in progress | 13% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.3000m pipe laid

Koothuparamba Proj AE 2
Date: 05/08/2022

Work in progress | 12% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.2800m pipe laid

Koothuparamba Proj AE 2
Date: 02/08/2022

Work in progress | 11% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.2450m pipe laid

Koothuparamba Proj AE 2
Date: 01/08/2022

Work in progress | 11% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.2400m pipe laid

Koothuparamba Proj AE 2
Date: 29/07/2022

Work in progress | 10% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.2250m pipe laid

Koothuparamba Proj AE 2
Date: 26/07/2022

Work in progress | 10% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.2000m pipe laid

Koothuparamba Proj AE 2
Date: 23/07/2022

Work in progress | 9% Completed

Work in progress 75% pipe supply completed. 1st & part bill submitted.1700m pipe laid

Koothuparamba Proj AE 2
Date: 21/07/2022

Work in progress | 9% Completed

Work in progres

Koothuparamba Proj AE 2
Date: 18/07/2022

Work in progress | 8% Completed

Work in progress

Attached images

img

Koothuparamba Proj AE 2
Date: 14/07/2022

Work in progress | 7% Completed

DI pipe laying work started

Attached images

img

Koothuparamba Proj AE 2
Date: 09/07/2022

Work in progress | 6% Completed

Pipe line work started

Koothuparamba Proj AE 2
Date: 01/07/2022

Work in progress | 5% Completed

50% pipe supplied