| Koothuparamba Proj AE 2 |
| Date: 31/10/2023 |
Work has been completed | 100% Completed
Work completed and 700 FHTC given 31.07.2023
| Koothuparamba Proj AE 2 |
| Date: 06/10/2023 |
Work has been completed | 100% Completed
Work completed
| Koothuparamba Proj AE 2 |
| Date: 10/08/2023 |
Work has been completed | 100% Completed
Work completed
| Koothuparamba Proj AE 2 |
| Date: 31/07/2023 |
Work has been completed | 100% Completed
Work completed
| Koothuparamba Proj AE 2 |
| Date: 26/07/2023 |
Work in progress | 92% Completed
Out of 700no FHTCs ,610nos given
| Koothuparamba Proj AE 2 |
| Date: 19/07/2023 |
Work in progress | 92% Completed
Out of 700no FHTCs ,600nos given
| Koothuparamba Proj AE 2 |
| Date: 14/07/2023 |
Work in progress | 91% Completed
Out of 700no FHTCs ,550nos given
| Koothuparamba Proj AE 2 |
| Date: 11/07/2023 |
Work in progress | 89% Completed
Out of 700no FHTCs ,500nos given
| Koothuparamba Proj AE 2 |
| Date: 05/07/2023 |
Work in progress | 85% Completed
Work in progress 65000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 30/06/2023 |
Work in progress | 80% Completed
Work in progress 64000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 23/06/2023 |
Work in progress | 79% Completed
Work in progress 63100m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 19/06/2023 |
Work in progress | 79% Completed
Work in progress 63000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 12/06/2023 |
Work in progress | 78% Completed
Work in progress 62500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 06/06/2023 |
Work in progress | 78% Completed
Work in progress 62000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 01/06/2023 |
Work in progress | 78% Completed
Work in progress 61000m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 25/05/2023 |
Work in progress | 78% Completed
Work in progress 60500m pipe laid Interconnection and charging work for already laid line in progress. HTC 470nos completed
| Koothuparamba Proj AE 2 |
| Date: 22/05/2023 |
Work in progress | 77% Completed
Work in progress, 60000m pipe laid, Interconnection and charging work for already laid line in progress. HTC 450nos completed
| Koothuparamba Proj AE 2 |
| Date: 17/05/2023 |
Work in progress | 77% Completed
Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 300nos completed
| Koothuparamba Proj AE 2 |
| Date: 10/05/2023 |
Work in progress | 76% Completed
Work in progress 57500m pipe laid Interconnection and charging work for already laid line in progress. HTC 270nos completed
| Koothuparamba Proj AE 2 |
| Date: 04/05/2023 |
Work in progress | 76% Completed
Work in progress 57200m pipe laid Interconnection and charging work for already laid line in progress. HTC 250nos completed
| Koothuparamba Proj AE 2 |
| Date: 28/04/2023 |
Work in progress | 75% Completed
Work in progress 56800m pipe laid Interconnection and charging work for already laid line in progress. HTC 200nos completed
| Koothuparamba Proj AE 2 |
| Date: 24/04/2023 |
Work in progress | 75% Completed
Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 172nos completed
| Koothuparamba Proj AE 2 |
| Date: 18/04/2023 |
Work in progress | 74% Completed
Work in progress 56200m pipe laid Interconnection and charging work for already laid line in progress. HTC 150nos completed
| Koothuparamba Proj AE 2 |
| Date: 10/04/2023 |
Work in progress | 74% Completed
Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 05/04/2023 |
Work in progress | 74% Completed
Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. HTC 100nos completed
| Koothuparamba Proj AE 2 |
| Date: 30/03/2023 |
Work in progress | 73% Completed
Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progress. second and part bill submitted
| Koothuparamba Proj AE 2 |
| Date: 18/03/2023 |
Work in progress | 73% Completed
Work in progress 56000m pipe laid Interconnection and charging work for already laid line in progres
| Koothuparamba Proj AE 2 |
| Date: 02/03/2023 |
Work in progress | 72% Completed
Work in progress ,Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 01/03/2023 |
Work in progress | 71% Completed
Work in progress ,Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 27/02/2023 |
Work in progress | 71% Completed
Work in progress 55890m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 23/02/2023 |
Work in progress | 70% Completed
Work in progress 55850m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 20/02/2023 |
Work in progress | 70% Completed
Work in progress 55800m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 17/02/2023 |
Work in progress | 69% Completed
Work in progress 55700m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 15/02/2023 |
Work in progress | 68% Completed
Work in progress 55500m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 10/02/2023 |
Work in progress | 68% Completed
Work in progress 55300m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 08/02/2023 |
Work in progress | 67% Completed
Work in progress 55000m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 01/02/2023 |
Work in progress | 67% Completed
Work in progress 54700m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 28/01/2023 |
Work in progress | 66% Completed
Work in progress 54600m pipe laid Interconnection and charging work for already laid line in progress
| Koothuparamba Proj AE 2 |
| Date: 25/01/2023 |
Work in progress | 65% Completed
Work in progress 54300m pipe laid Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 23/01/2023 |
Work in progress | 65% Completed
Work in progress 54100m pipe laid Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 19/01/2023 |
Work in progress | 65% Completed
Work in progress 54000m pipe laid Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 18/01/2023 |
| Koothuparamba Proj AE 2 |
| Date: 16/01/2023 |
Work in progress | 54% Completed
Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 13/01/2023 |
Work in progress | 54% Completed
Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 11/01/2023 |
Work in progress | 53% Completed
Interconnection and charging work for already laid line in progress.
| Koothuparamba Proj AE 2 |
| Date: 10/01/2023 |
Work in progress | 52% Completed
Work in progress 52000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 08/01/2023 |
Work in progress | 50% Completed
Work in progress 50250m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 06/01/2023 |
Work in progress | 47% Completed
Work in progress 48100m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 31/12/2022 |
Work in progress | 45% Completed
Work in progress 35600m pipe laid and pressure test for Pipe is in progress
| Koothuparamba Proj AE 2 |
| Date: 29/12/2022 |
Work in progress | 41% Completed
Work in progress 35000m pipe laid and pressure test for Pipe is in progress
| Koothuparamba Proj AE 2 |
| Date: 28/12/2022 |
Work in progress | 40% Completed
work in progress 35000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 17/12/2022 |
Work in progress | 38% Completed
Work in progress 30000 m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 30/11/2022 |
Work in progress | 35% Completed
Work in progress 26200 m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 23/11/2022 |
Work in progress | 34% Completed
34 % of work completed 25000 m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 19/11/2022 |
Work in progress | 33% Completed
Work in progress.24325m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 14/11/2022 |
Work in progress | 33% Completed
Work in progress.24300m pipe laid. DI pipe laying completed.
| Koothuparamba Proj AE 2 |
| Date: 11/11/2022 |
Work in progress | 33% Completed
Work in progress.22500m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 02/11/2022 |
Work in progress | 31% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.17500m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 27/10/2022 |
Work in progress | 30% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.16600m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 24/10/2022 |
Work in progress | 30% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.165000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 21/10/2022 |
Work in progress | 29% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.16000m pipe laid View all updates
| Koothuparamba Proj AE 2 |
| Date: 17/10/2022 |
Work in progress | 28% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.14000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 13/10/2022 |
Work in progress | 27% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.13000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 10/10/2022 |
Work in progress | 26% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.12000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 06/10/2022 |
Work in progress | 25% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.9000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 30/09/2022 |
Work in progress | 24% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.8500m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 27/09/2022 |
Work in progress | 23% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.8000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 20/09/2022 |
Work in progress | 22% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.8000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 12/09/2022 |
Work in progress | 20% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.7000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 05/09/2022 |
Work in progress | 19% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.5800m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 30/08/2022 |
Work in progress | 18% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.5800m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 27/08/2022 |
Work in progress | 17% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.5700m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 24/08/2022 |
Work in progress | 17% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.5500m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 20/08/2022 |
Work in progress | 16% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.4500m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 16/08/2022 |
Work in progress | 15% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.4000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 10/08/2022 |
Work in progress | 13% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.3000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 05/08/2022 |
Work in progress | 12% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.2800m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 02/08/2022 |
Work in progress | 11% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.2450m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 01/08/2022 |
Work in progress | 11% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.2400m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 29/07/2022 |
Work in progress | 10% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.2250m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 26/07/2022 |
Work in progress | 10% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.2000m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 23/07/2022 |
Work in progress | 9% Completed
Work in progress 75% pipe supply completed. 1st & part bill submitted.1700m pipe laid
| Koothuparamba Proj AE 2 |
| Date: 21/07/2022 |
Work in progress | 9% Completed
Work in progres
| Koothuparamba Proj AE 2 |
| Date: 18/07/2022 |
| Koothuparamba Proj AE 2 |
| Date: 14/07/2022 |
| Koothuparamba Proj AE 2 |
| Date: 09/07/2022 |
Work in progress | 6% Completed
Pipe line work started