Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kattappana AEE 1
Date: 25/05/2023

Work has been completed | 100% Completed

work is completed.

Kattappana AEE 1
Date: 24/05/2023

Work in progress | 99% Completed

work is completed.

Kattappana AEE 1
Date: 23/05/2023

Work in progress | 99% Completed

work is completed.

Kattapana AE 1
Date: 22/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 21/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 20/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 19/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 18/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 17/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 16/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 15/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 13/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 12/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 10/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 09/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 08/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattapana AE 1
Date: 06/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 05/05/2023

Work has started | 0% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 03/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing

Kattappana AEE 1
Date: 01/05/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 29/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 28/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 27/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 26/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 25/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 24/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 22/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 21/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 20/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.

Kattappana AEE 1
Date: 19/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed .

Kattappana AEE 1
Date: 18/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed .

Kattappana AEE 1
Date: 17/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed .

Kattappana AEE 1
Date: 15/04/2023

Work in progress | 90% Completed

2460m of 100 mm GI Pipe laid work and all other parallel works are completed .

Kattappana AEE 1
Date: 14/04/2023

Work in progress | 90% Completed

2433m of 100 mm GI Pipe laid work completed and to do only welding work .

Attached images

img

Kattappana AEE 1
Date: 13/04/2023

Work in progress | 88% Completed

2428m of 100 mm GI Pipe laid work completed and to do only welding work .

Attached images

img img

Kattappana AEE 1
Date: 12/04/2023

Work in progress | 86% Completed

2425m of 100 mm GI Pipe laid work completed and to do only welding work .

Attached images

img

Kattappana AEE 1
Date: 11/04/2023

Work in progress | 85% Completed

2395m of 100 mm GI Pipe laid work completed and to do only welding work .

Attached images

img

Kattappana AEE 1
Date: 10/04/2023

Work in progress | 84% Completed

2392 m of 100 mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 08/04/2023

Work in progress | 82% Completed

2388 m of 100 mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 05/04/2023

Work in progress | 80% Completed

2274 m of 100 mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 04/04/2023

Work in progress | 78% Completed

2058 m of 100 mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 01/04/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattapana AE 1
Date: 30/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattapana AE 1
Date: 29/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattapana AE 1
Date: 28/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattappana AEE 1
Date: 27/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattappana AEE 1
Date: 25/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattappana AEE 1
Date: 24/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattappana AEE 1
Date: 23/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.

Kattapana AE 1
Date: 22/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 20/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 17/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 16/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 14/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 13/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 10/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 09/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 08/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 07/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 06/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 03/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 02/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 01/03/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 28/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 25/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 24/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 23/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 22/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 21/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 20/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 17/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 14/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 13/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. work is ongoing on site

Kattapana AE 1
Date: 10/02/2023

Work in progress | 76% Completed

1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 09/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 08/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 07/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattapana AE 1
Date: 06/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 04/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 03/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 02/02/2023

Work in progress | 76% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 01/02/2023

Work in progress | 75% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site

Kattappana AEE 1
Date: 31/01/2023

Work in progress | 75% Completed

1866m of 100mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 30/01/2023

Work in progress | 62% Completed

1512m of 100mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 28/01/2023

Work in progress | 55% Completed

1428m of 100mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 27/01/2023

Work in progress | 46% Completed

1128m of 100mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 26/01/2023

Work in progress | 40% Completed

972m of 100mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 25/01/2023

Work in progress | 32% Completed

786m of 100mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 24/01/2023

Work in progress | 26% Completed

642m of 100mm GI Pipes laid and to do the Welding work at site.

Kattappana AEE 1
Date: 23/01/2023

Work in progress | 20% Completed

486m of 100mm GI Pipes laid and to do the Welding work at site.

Attached images

img

Kattappana AEE 1
Date: 21/01/2023

Work in progress | 16% Completed

384m of 100mm GI Pipes laid.

Attached images

img

Kattappana AEE 1
Date: 20/01/2023

Work in progress | 11% Completed

264m of 100mm GI Pipes laid.

Kattappana AEE 1
Date: 19/01/2023

Work in progress | 6% Completed

144m of 100mm GI Pipes laid.

Kattappana AEE 1
Date: 18/01/2023

Work in progress | 1% Completed

Work started at site.