| Kattappana AEE 1 |
| Date: 25/05/2023 |
Work has been completed | 100% Completed
work is completed.
| Kattappana AEE 1 |
| Date: 24/05/2023 |
Work in progress | 99% Completed
work is completed.
| Kattappana AEE 1 |
| Date: 23/05/2023 |
Work in progress | 99% Completed
work is completed.
| Kattapana AE 1 |
| Date: 22/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 21/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 20/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 19/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 18/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 17/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 16/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 15/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 13/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 12/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 10/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 09/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 08/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattapana AE 1 |
| Date: 06/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 05/05/2023 |
Work has started | 0% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 03/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing
| Kattappana AEE 1 |
| Date: 01/05/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 29/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 28/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 27/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 26/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 25/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 24/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 22/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 21/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 20/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing.
| Kattappana AEE 1 |
| Date: 19/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed .
| Kattappana AEE 1 |
| Date: 18/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed .
| Kattappana AEE 1 |
| Date: 17/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed .
| Kattappana AEE 1 |
| Date: 15/04/2023 |
Work in progress | 90% Completed
2460m of 100 mm GI Pipe laid work and all other parallel works are completed .
| Kattappana AEE 1 |
| Date: 14/04/2023 |
| Kattappana AEE 1 |
| Date: 13/04/2023 |
| Kattappana AEE 1 |
| Date: 12/04/2023 |
| Kattappana AEE 1 |
| Date: 11/04/2023 |
| Kattappana AEE 1 |
| Date: 10/04/2023 |
Work in progress | 84% Completed
2392 m of 100 mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 08/04/2023 |
Work in progress | 82% Completed
2388 m of 100 mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 05/04/2023 |
| Kattappana AEE 1 |
| Date: 04/04/2023 |
| Kattappana AEE 1 |
| Date: 01/04/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattapana AE 1 |
| Date: 30/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattapana AE 1 |
| Date: 29/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattapana AE 1 |
| Date: 28/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattappana AEE 1 |
| Date: 27/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattappana AEE 1 |
| Date: 25/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattappana AEE 1 |
| Date: 24/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattappana AEE 1 |
| Date: 23/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site.
| Kattapana AE 1 |
| Date: 22/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 20/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 17/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 16/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 14/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 13/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 10/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 09/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 08/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 07/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 06/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 03/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 02/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 01/03/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 28/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 25/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 24/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 23/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 22/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 21/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 20/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 17/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 14/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 13/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. work is ongoing on site
| Kattapana AE 1 |
| Date: 10/02/2023 |
Work in progress | 76% Completed
1866 m of 100 mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 09/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 08/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 07/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattapana AE 1 |
| Date: 06/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 04/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 03/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 02/02/2023 |
Work in progress | 76% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 01/02/2023 |
Work in progress | 75% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site. no work is going on site
| Kattappana AEE 1 |
| Date: 31/01/2023 |
Work in progress | 75% Completed
1866m of 100mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 30/01/2023 |
| Kattappana AEE 1 |
| Date: 28/01/2023 |
Work in progress | 55% Completed
1428m of 100mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 27/01/2023 |
Work in progress | 46% Completed
1128m of 100mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 26/01/2023 |
| Kattappana AEE 1 |
| Date: 25/01/2023 |
| Kattappana AEE 1 |
| Date: 24/01/2023 |
Work in progress | 26% Completed
642m of 100mm GI Pipes laid and to do the Welding work at site.
| Kattappana AEE 1 |
| Date: 23/01/2023 |
| Kattappana AEE 1 |
| Date: 21/01/2023 |
| Kattappana AEE 1 |
| Date: 20/01/2023 |
Work in progress | 11% Completed
264m of 100mm GI Pipes laid.
| Kattappana AEE 1 |
| Date: 19/01/2023 |
Work in progress | 6% Completed
144m of 100mm GI Pipes laid.
| Kattappana AEE 1 |
| Date: 18/01/2023 |
Work in progress | 1% Completed
Work started at site.