| Painavu PH Section AE |
| Date: 27/04/2023 |
Work has been completed | 100% Completed
Work Completed on 17/04/2022
| Painavu PH Section AE |
| Date: 13/04/2023 |
Work in progress | 95% Completed
Road Crossing Work Completed on 13/04/2023
| Painavu PH Section AE |
| Date: 11/04/2023 |
Work in progress | 89% Completed
Contractor has arranged Road Crossing Work. Work is going on
| Painavu PH Section AE |
| Date: 31/03/2023 |
Work in progress | 85% Completed
Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line
| Painavu PH Section AE |
| Date: 28/03/2023 |
Work in progress | 80% Completed
Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line
| Painavu PH Section AE |
| Date: 23/03/2023 |
Work in progress | 80% Completed
Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line
| Painavu PH Section AE |
| Date: 16/03/2023 |
Work in progress | 80% Completed
Road restoration amount payment completed waiting for sanction letter from PWD. Road cutting agreement executed with PWD
| Painavu PH Section AE |
| Date: 08/03/2023 |
Work in progress | 72% Completed
Road restoration amount payment completed waiting for sanction letter from PWD
| Painavu PH Section AE |
| Date: 27/02/2023 |
Work in progress | 72% Completed
Road restoration amount payment completed waiting for sanction letter from PWD
| Painavu PH Section AE |
| Date: 21/02/2023 |
Work in progress | 72% Completed
Road restoration amount payment completed waiting for sanction letter from PWD.
| Painavu PH Section AE |
| Date: 14/02/2023 |
Work in progress | 70% Completed
Road cutting permission procedures going on
| Painavu PH Section AE |
| Date: 06/02/2023 |
Work in progress | 70% Completed
Road cutting permission procedures going on
| Painavu PH Section AE |
| Date: 25/01/2023 |
Work in progress | 70% Completed
Road Cutting permission procedures going on
| Painavu PH Section AE |
| Date: 20/01/2023 |
Work in progress | 69% Completed
Permission was granted to cut the road
| Painavu PH Section AE |
| Date: 10/01/2023 |
Work in progress | 66% Completed
Pipe laying work is going on
| Painavu PH Section AE |
| Date: 04/01/2023 |
Work in progress | 63% Completed
Pipe laying in progress
| Painavu PH Section AE |
| Date: 26/12/2022 |
Work in progress | 60% Completed
Pipe Laying in Progress
| Painavu PH Section AE |
| Date: 17/12/2022 |
Work in progress | 56% Completed
Pipe Laying Works in Progress
| Painavu PH Section AE |
| Date: 13/12/2022 |
Work in progress | 55% Completed
Pipe Laying in Progress
| Painavu PH Section AE |
| Date: 08/12/2022 |
Work in progress | 52% Completed
Work in progress
| Painavu PH Section AE |
| Date: 03/12/2022 |
Work in progress | 47% Completed
Work in progress
| Painavu PH Section AE |
| Date: 29/11/2022 |
Work in progress | 45% Completed
Work on going
| Painavu PH Section AE |
| Date: 24/11/2022 |
Work in progress | 30% Completed
Work on going
| Painavu PH Section AE |
| Date: 16/11/2022 |
Work in progress | 10% Completed
pipe supply done, work started
| Painavu PH Sub Dn AEE |
| Date: 06/11/2022 |
Work in progress | 5% Completed
work started
| Painavu PH Sub Dn AEE |
| Date: 15/10/2022 |
Work has started | 0% Completed
pipe test conducted on 14.10.22
| Painavu PH Section AE |
| Date: 03/10/2022 |
Work in progress | 0% Completed
pipe supply order placed in the firm
| Painavu PH Sub Dn AEE |
| Date: 02/10/2022 |
Work has started | 0% Completed
pipe supply order placed in the firm
| Painavu PH Sub Dn AEE |
| Date: 20/09/2022 |
Work has started | 0% Completed
Agreement executed
| Painavu PH Sub Dn AEE |
| Date: 15/09/2022 |
Work in progress | 0% Completed
Agreement executed
| Painavu PH Section AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
work order issued
| Painavu PH Section AE |
| Date: 01/09/2022 |
Work has started | 0% Completed
work order issued
| Thodupuzha PH Dn EE |
| Date: 27/08/2022 |
Work has started | 0% Completed
Work Order Issued