Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Painavu PH Section AE
Date: 27/04/2023

Work has been completed | 100% Completed

Work Completed on 17/04/2022

Painavu PH Section AE
Date: 13/04/2023

Work in progress | 95% Completed

Road Crossing Work Completed on 13/04/2023

Painavu PH Section AE
Date: 11/04/2023

Work in progress | 89% Completed

Contractor has arranged Road Crossing Work. Work is going on

Painavu PH Section AE
Date: 31/03/2023

Work in progress | 85% Completed

Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line

Painavu PH Section AE
Date: 28/03/2023

Work in progress | 80% Completed

Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line

Painavu PH Section AE
Date: 23/03/2023

Work in progress | 80% Completed

Road Cutting sanction received from PWD. Work arranged to interconnect this branch line with existing line

Painavu PH Section AE
Date: 16/03/2023

Work in progress | 80% Completed

Road restoration amount payment completed waiting for sanction letter from PWD. Road cutting agreement executed with PWD

Painavu PH Section AE
Date: 08/03/2023

Work in progress | 72% Completed

Road restoration amount payment completed waiting for sanction letter from PWD

Painavu PH Section AE
Date: 27/02/2023

Work in progress | 72% Completed

Road restoration amount payment completed waiting for sanction letter from PWD

Painavu PH Section AE
Date: 21/02/2023

Work in progress | 72% Completed

Road restoration amount payment completed waiting for sanction letter from PWD.

Painavu PH Section AE
Date: 14/02/2023

Work in progress | 70% Completed

Road cutting permission procedures going on

Painavu PH Section AE
Date: 06/02/2023

Work in progress | 70% Completed

Road cutting permission procedures going on

Painavu PH Section AE
Date: 25/01/2023

Work in progress | 70% Completed

Road Cutting permission procedures going on

Painavu PH Section AE
Date: 20/01/2023

Work in progress | 69% Completed

Permission was granted to cut the road

Painavu PH Section AE
Date: 10/01/2023

Work in progress | 66% Completed

Pipe laying work is going on

Painavu PH Section AE
Date: 04/01/2023

Work in progress | 63% Completed

Pipe laying in progress

Painavu PH Section AE
Date: 26/12/2022

Work in progress | 60% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 17/12/2022

Work in progress | 56% Completed

Pipe Laying Works in Progress

Painavu PH Section AE
Date: 13/12/2022

Work in progress | 55% Completed

Pipe Laying in Progress

Painavu PH Section AE
Date: 08/12/2022

Work in progress | 52% Completed

Work in progress

Painavu PH Section AE
Date: 03/12/2022

Work in progress | 47% Completed

Work in progress

Painavu PH Section AE
Date: 29/11/2022

Work in progress | 45% Completed

Work on going

Painavu PH Section AE
Date: 24/11/2022

Work in progress | 30% Completed

Work on going

Painavu PH Section AE
Date: 16/11/2022

Work in progress | 10% Completed

pipe supply done, work started

Painavu PH Sub Dn AEE
Date: 06/11/2022

Work in progress | 5% Completed

work started

Painavu PH Sub Dn AEE
Date: 15/10/2022

Work has started | 0% Completed

pipe test conducted on 14.10.22

Painavu PH Section AE
Date: 03/10/2022

Work in progress | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 02/10/2022

Work has started | 0% Completed

pipe supply order placed in the firm

Painavu PH Sub Dn AEE
Date: 20/09/2022

Work has started | 0% Completed

Agreement executed

Painavu PH Sub Dn AEE
Date: 15/09/2022

Work in progress | 0% Completed

Agreement executed

Painavu PH Section AE
Date: 13/09/2022

Work has started | 0% Completed

work order issued

Painavu PH Section AE
Date: 01/09/2022

Work has started | 0% Completed

work order issued

Thodupuzha PH Dn EE
Date: 27/08/2022

Work has started | 0% Completed

Work Order Issued