| Kannur WS Sn AE 2 |
| Date: 06/12/2024 |
Work has been completed | 100% Completed
CC fifth & final bill submitted.
| Kannur WS Sn AE 2 |
| Date: 05/12/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 02/12/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 29/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 26/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 23/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 21/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 18/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 15/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 12/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 09/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 06/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 03/11/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 31/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 28/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 25/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 22/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 20/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 17/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 14/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 11/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 08/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 05/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 02/10/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable
| Kannur WS Sn AE 2 |
| Date: 29/09/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favourable
| Kannur WS Sn AE 2 |
| Date: 26/09/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favourable
| Kannur WS Sn AE 2 |
| Date: 23/09/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favourable
| Kannur WS Sn AE 2 |
| Date: 20/09/2024 |
Work in progress | 98% Completed
Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 08/09/2024 |
Work in progress | 98% Completed
Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 04/09/2024 |
Work in progress | 98% Completed
Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 01/09/2024 |
Work in progress | 98% Completed
Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 31/08/2024 |
Work in progress | 98% Completed
Pipe laid 12000 m out of 12000 m and FHTC 799 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 29/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 760 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 25/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 760 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 22/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 740 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 19/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 740 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 16/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 740 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 13/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 740 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 10/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 07/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 04/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 01/08/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed
| Kannur WS Sn AE 2 |
| Date: 29/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 26/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 23/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 20/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 17/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 730 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 14/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 720 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 11/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 678Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 08/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 05/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 02/07/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 29/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 26/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 675Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 23/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 20/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 17/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 14/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 672 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 11/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 08/06/2024 |
Work in progress | 98% Completed
Pipe laid 11800 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 05/06/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 670 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 02/06/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 30/05/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 665Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 27/05/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 660Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 24/05/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 760 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 21/05/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 535 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 18/05/2024 |
Work in progress | 83% Completed
Pipe laid 11250 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 15/05/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 12/05/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 09/05/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 06/05/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 03/05/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 30/04/2024 |
Work in progress | 83% Completed
Pipe laid 11200 m out of 12000 m and FHTC 530 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 27/04/2024 |
Work in progress | 83% Completed
Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed.
| Kannur WS Sn AE 2 |
| Date: 23/04/2024 |
Work in progress | 83% Completed
Pipe laid 10000 m out of 12000 m and FHTC 480 Nos out of 740 Nos completed.