Malappuram Project Dn AE6 |
Date: 15/03/2021 |
Work has been completed | 100% Completed
completed
Malappuram Project Dn AE6 |
Date: 09/03/2021 |
Work has been completed | 100% Completed
completed
Malappuram Project Dn AE6 |
Date: 07/03/2021 |
Work in progress | 99% Completed
work completed, final bill under preparation
Malappuram Project Dn AE6 |
Date: 01/03/2021 |
Work in progress | 96% Completed
all panchayath survey sketch submitted
Malappuram Project Dn AE6 |
Date: 25/02/2021 |
Work in progress | 96% Completed
all panchayath survey sketch submitted
Malappuram Project Dn AE6 |
Date: 24/02/2021 |
Work in progress | 96% Completed
all panchayath survey sketch submitted
Malappuram Project Dn AE6 |
Date: 23/02/2021 |
Work in progress | 96% Completed
all panchayath survey sketch submitted
Malappuram Project Dn AE6 |
Date: 20/02/2021 |
Work in progress | 95% Completed
survey sketch submitted
Malappuram Project Dn AE6 |
Date: 18/02/2021 |
Work in progress | 93% Completed
the hard copy of survey sketch submitted for verification
Malappuram Project Dn AE6 |
Date: 17/02/2021 |
Work in progress | 93% Completed
the hard copy of survey sketch submitted for verification
Malappuram Project Dn AE6 |
Date: 09/02/2021 |
Work in progress | 92% Completed
4 panchayath drawings submitted and remaing 4 panchayath under scrutiny
Malappuram Project Dn AE6 |
Date: 05/02/2021 |
Work in progress | 91% Completed
survey drawing of five panchayath under scrutiny
Malappuram Project Dn AE6 |
Date: 24/01/2021 |
Work in progress | 91% Completed
survey completed, drawings under preparation
Malappuram Project Dn AE6 |
Date: 17/11/2020 |
Work in progress | 90% Completed
90 percentage of the work completed
Malappuram Project Dn AE6 |
Date: 12/11/2020 |
Work in progress | 80% Completed
80 percentage of work completed
Malappuram Project Dn AE6 |
Date: 05/09/2020 |
Work has started | 0% Completed
work tendered