| Kollam WS Sn 2 - AE |
| Date: 23/10/2026 |
| Kollam WS Sn 2 - AE |
| Date: 15/10/2026 |
Work in progress | 61% Completed
Alteration of house connection works going on
| Kollam WS Sn 2 - AE |
| Date: 06/10/2026 |
Work in progress | 61% Completed
Alteration of house connection works going on
| Kollam WS Sn 2 - AE |
| Date: 01/10/2026 |
| Kollam WS Sn 2 - AE |
| Date: 23/09/2026 |
| Kollam WS Sn 2 - AE |
| Date: 19/09/2026 |
| Kollam WS Sn 2 - AE |
| Date: 14/09/2026 |
| Kollam WS Sn 2 - AE |
| Date: 11/09/2026 |
Work in progress | 20% Completed
Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 1100 m pipe laid -20% completed.
| Kollam WS Sn 2 - AE |
| Date: 09/09/2026 |
| Kollam WS Sn 2 - AE |
| Date: 08/09/2026 |
Work in progress | 5% Completed
Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing.
| Kollam WS Sn 2 - AE |
| Date: 01/09/2026 |
Work in progress | 1% Completed
Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work started and progressing.
| Kollam WS Sn 2 - AE |
| Date: 31/08/2026 |
Work in progress | 1% Completed
pipe testing completed and pipe supplied
| Kollam WS Sn 2 - AE |
| Date: 22/08/2026 |
Work in progress | 1% Completed
pipe testing completed and pipe supplied