Kollam WS Sn 2 - AE
Date: 23/10/2026

Work in progress | 70% Completed

Alteration works and AC plugging works are goin on

Attached images

img img img

Kollam WS Sn 2 - AE
Date: 15/10/2026

Work in progress | 61% Completed

Alteration of house connection works going on

Kollam WS Sn 2 - AE
Date: 06/10/2026

Work in progress | 61% Completed

Alteration of house connection works going on

Kollam WS Sn 2 - AE
Date: 01/10/2026

Work in progress | 60% Completed

Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 2700 m pipe laid -60% completed.... Laying near Poovanpuzha thaikkavu road progressing

Attached images

img

Kollam WS Sn 2 - AE
Date: 23/09/2026

Work in progress | 60% Completed

Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 2700 m pipe laid -60% completed.

Attached images

img

Kollam WS Sn 2 - AE
Date: 19/09/2026

Work in progress | 40% Completed

Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 2100 m pipe laid -40% completed.

Attached images

img img

Kollam WS Sn 2 - AE
Date: 14/09/2026

Work in progress | 35% Completed

Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 1782 m pipe laid -35% completed.

Attached images

img

Kollam WS Sn 2 - AE
Date: 11/09/2026

Work in progress | 20% Completed

Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing- Out of 4000 M 1100 m pipe laid -20% completed.

Kollam WS Sn 2 - AE
Date: 09/09/2026

Work in progress | 8% Completed

Pipe laying work in progressing

Attached images

img

Kollam WS Sn 2 - AE
Date: 08/09/2026

Work in progress | 5% Completed

Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work in progressing.

Kollam WS Sn 2 - AE
Date: 01/09/2026

Work in progress | 1% Completed

Package 4- Sakthikulangra& Thrikkadavoor area- Pipe laying work started and progressing.

Kollam WS Sn 2 - AE
Date: 31/08/2026

Work in progress | 1% Completed

pipe testing completed and pipe supplied

Kollam WS Sn 2 - AE
Date: 22/08/2026

Work in progress | 1% Completed

pipe testing completed and pipe supplied